Categories
Announcements Stations Subways

View the final designs for two Spadina Subway stations!

spadina-stations-final-designs_2010_07_06

On Thursday, July 8, and Tuesday, July 13, 2010, you are invited to view the final designs of two stations along the Spadina Subway extension: Sheppard West Station and Highway 407 Station.

The Toronto-York Spadina Subway Extension project will extend 8.6 kilometres north from Toronto’s Downsview Station to the Vaughan Metropolitan Centre at Highway 7. The project will better connect people to their destinations of choice, and will help Vaughan fulfill its vision for future growth and development.

We encourage you to attend these two public open houses and share the excitement as rapid transit plans move forward in York Region.

Sheppard West Station Public Open House

Date: Thursday, July 8, 2010
Time: 4 – 7:30pm
Location: TTC Downsview Station – Bus Terminal Platform
At the intersection of Allen Road and Sheppard Avenue West
Access to Bus Terminal Platform through “Passenger Pick up and Drop off”

Highway 407 Station Public Open House

Date: Tuesday, July 13, 2010
Time: 6:30 – 8:30pm
Location: The Hilton Garden Inn – Toscana Centre
3201 Highway 7, Vaughan

Take Transit: From Downsview Station take Viva Orange 077/077A or Viva Orange 107 to arrive at the doorstep of the Hilton Garden Inn, at the intersection of Highway 7 and Edgeley/Interchange Way.

Categories
Announcements Stations Subways

Come see three Spadina Subway station designs at once!

A map of the Spadina subway extension.

Extending from Downsview Station in Toronto to the Vaughan Metropolitan Centre at Highway 7 in Vaughan, the Spadina subway extension will cover a total of 8.6 kilometres and include six new stations.

To date, three separate public open houses have been held to share the preliminary station design concepts with the community: Sheppard West Station on November 17, 2009, York University Station on December 3, 2009, and the Steeles West Station on February 3, 2010.

If you happened to miss the February public open house, you now have another opportunity to check out the preliminary design concept for the Steeles West Station, and be among the first to review the preliminary design concepts for the Vaughan Metropolitan Centre and the Highway 407 Stations. All three will be on display together at a public open house on Wednesday, March 10, 2010.

The preliminary design concept for the remaining new station – Finch West Station – will be presented to the public later this spring. Also, more open houses will be held later this year to share more detailed architectural concepts for all six stations so stay tuned.

Public Open House for Vaughan Metropolitan Centre, Highway 407 and Steeles West Subway Stations

Date: Wednesday, March 10, 2010
Time: 6:30 p.m. to 8:30 p.m.
Location: The Hilton Garden Inn, Toscana Centre
3201 Highway 7, Vaughan, ON
Categories
Announcements Stations Subways

Station designs for Spadina Subway extension continue to take shape!

An aerial view of the Steeles West Station design
An aerial view of the Steeles West Station design

In the fall of 2009, preliminary station designs were unveiled at public open houses for two of the six stations that will be located along vivaNext’s 8.6 kilometre Spadina subway extension, which will extend from Downsview Station in Toronto to Vaughan Metropolitan Centre Station in Vaughan.

Next week, on Wednesday, February 3, 2010, the preliminary design for a third station – Steeles West – will also be unveiled at a public open house and you are invited to attend.

As previously mentioned on this blog, all of the six stations that will be built along the Spadina subway extension will have a unique design. The most striking features of the Steeles West station preliminary design are its very distinctive and futuristic profile, and its central light cone, which allows daylight to reach all the way down to the platform levels. It’s truly something you have to see for yourself to appreciate.

Following this public open house, a second one featuring more detailed architectural concepts will take place for the Steeles West station in the spring of 2010. Preliminary designs for the remaining Spadina subway extension stations – Finch West, Highway 407 and Vaughan Metropolitan Centre – will also be unveiled in the coming months.

Steeles West Subway Station Public Open House
Date: Wednesday, February 3, 2010
Time: 6:30 pm – 8:30 pm
Location: Black Creek Pioneer Village,  Garfield Weston Room
1000 Murray Ross Parkway, Toronto, ON

Categories
Announcements General Urban Planning vivaNext.com

Reflecting back on a year of many milestones!

With a new year just around the corner, we wanted to celebrate by reflecting back on some significant milestones for vivaNext in 2009.

In early spring, the Province of Ontario committed $1.4 billion for the construction of dedicated rapidways along Davis Drive, Highway 7 and Yonge Street for Viva vehicles.

The following month, the Ministry of the Environment unconditionally approved the Environmental Project Report for the proposed Yonge subway extension.

Around this time, our new website was also launched along with this blog and other social media initiatives to help keep you informed of all the latest vivaNext developments.

By the fall, preliminary rapidway construction activities were underway in Newmarket and Markham, and a contract for conceptual design work regarding the Yonge subway extension was awarded. In addition, preliminary station designs were also unveiled for several of the Spadina subway extension stations at a series of public open houses, and the project took an important step forward with a groundbreaking ceremony at the Wilson Subway Yard.

Then, just before the holiday season, a ceremony was held on the site of the planned rapidway alongside Enterprise Drive in Markham (which is part of the Highway 7 rapidway project) to commemorate the start of construction of the first 37 km of rapidways.

From every side of York Region, this past year has been filled with milestones for the vivaNext projects. We look forward to bringing you many more in 2010.

Happy New Year from vivaNext!

Reminder: All YRT\Viva rides are free on New Year’s Eve after 7 p.m.

Categories
Announcements Press Stations Subways

The Spadina subway extension moves forward!

From left: Vaughan Mayor Linda Jackson, Ontario Minister of Transportation Jim Bradley, Toronto Mayor David Miller, Federal Minister of Finance Jim Flaherty and TTC Chair Adam Giambrone begin the work on the Spadina subway extension.
From left: Vaughan Mayor Linda Jackson, Ontario Transportation Jim Bradley, Toronto Mayor David Miller, Federal Finance Minister Jim Flaherty and TTC Chair Adam Giambrone begin work on the Spadina subway extension Friday.

This past Friday, November 27, 2009, a groundbreaking ceremony of a link that will connect the future Spadina subway extension mainline to the existing Wilson Subway Yard and expand yard storage facilities was held.

Government dignitaries in attendance at the Wilson Yard connection site included the Honourable Jim Flaherty, Canada’s Minister of Finance; the Honourable Jim Bradley, Ontario Transportation Minister; His Worship David Miller, Mayor of Toronto; Her Worship Linda Jackson, Mayor of Vaughan; and Toronto Transit Commission chair Adam Giambrone.

“This is another significant step forward that will help meet the Greater Toronto Area’s future network needs,” said York Region Chairman and CEO Bill Fisch. “As York Region continues to grow and mature, it is imperative to have the proper infrastructure and resources in place for both residents and businesses today and in the future.”

Extending from the Downsview Station in Toronto to the Vaughan Metropolitan Centre Station in Vaughan, the Spadina subway extension will cover a total of 8.6 kilometres and include six stations. Every day, almost as many people travel north to York Region from Toronto as vice versa — including many of the 50,000 students and staff who study and work at York University.

The completion date for the Spadina subway extension is 2015. The $2.6 billion funding required for the project has been secured from all levels of government including $697 million from the Government of Canada, $870 million from the Province of Ontario, $352 million from York Region and $526 million from the City of Toronto.

Categories
Going Green Stations Subways

There is light at the end of the Steeles West subway tunnel!

An artist rendering of the Steeles West subway station.
An artist rendering of the Steeles West subway station.

Each of the six subway stations that will be built along the Spadina subway extension – a key part of the vivaNext plan – will have a unique design.

Above ground, the most striking feature of the Steeles West Station conceptual design is its very distinctive and futuristic profile. It looks like something right out of ‘The Jetsons’. Below ground, a central light cone will bring daylight all the way down to the platform levels – a solution that’s both illuminating and eco-friendly.

The Steeles West subway station will also feature a commuter parking lot with 1,900 parking spaces plus two bus terminals, including one for YRT and Viva.

Planned service frequency from Downsview Station to Steeles West Station is every two minutes, and from Steeles West Station to Vaughan Metropolitan Centre Station, every five minutes.

Categories
Community Events Rapidways Subways

York University students get an A+ for enthusiasm!

Team vivaNext member, Donald, shows students where the new Spadina subway extension will run on a map during the Annual Clubs BBQ last Wednesday.
Team vivaNext member, Donald, shows students where the new Spadina subway extension will run on a map during the Annual Clubs BBQ last Wednesday.

VivaNext teams had such a great time talking to York University students on campus last week about how our new rapidways and subway extensions will make it faster and easier to get to school in the future. Over a two-day period, we had the opportunity to speak to hundreds of students who use rapid transit to commute to class from all over York Region. Boy, did they get excited when they learned that rapidway stops will be near their campus within the next four years, and subway stops right on their campus within the next six years.

On Wednesday, our first day on campus, we were at the Annual Clubs BBQ at Vanier Field. While the line-up for burgers was incredibly long, the one at our vivaNext booth was pretty impressive as well. Then the next day, Thursday, we took part in the Transportation Fair at York Lanes along with other transit organizations, car share companies and cycling networks. It gave York University students a chance to explore a wide range of present and future commuting options – including Viva – all in one convenient location.

Perhaps you were there? If so, we’d love to hear what you think about the vivaNext plan and what impressed you the most.

Categories
Announcements Press Subways

Big step toward starting construction on the Spadina subway extension

Chair Fisch and the other dignitaries pose for cameras in front of a scale model of a tunnel boring machine.
Chair Fisch and the other dignitaries pose for cameras in front of a scale model of a tunnel boring machine.

Lovat, an Ontario-based company that makes tunnel boring equipment, has been awarded a $58-million contract to build four machines that will be used in the construction of the Spadina subway extension.

The announcement was made last Friday, August 7, at the Lovat plant by Ontario Transportation Minister Jim Bradley, joined by MP Bob Dechert, York Regional Chair and CEO Bill Fisch, TTC Chair Adam Giambrone and Lovat President Dick Cooper. Not only does this mean the creation of some 200 jobs in the GTA and a boost to the economy, it signals continued progress on the project as it’s scheduled to open in 2015.

Prior to the announcement, I had the pleasure of joining the group for a bit of a tour of Lovat. We met at one end of their Mississauga plant and walked through to the other end while learning about what’s involved in making tunnel boring equipment. Cameras and reporters were waiting at the end of the tour to hear each dignitary deliver a short speech about the announcement.

It was awe-inspiring to watch the dignitaries being interviewed in front of a massive tunnel boring machine. They’re HUGE. Just take a look at the picture below to see how big they are compared to the people near them.

Lovat has built similar and even larger machines for projects all around the world, from Algeria to Venezuela. “We are pleased to be a part of this significant mass-transit project, as it not only generates jobs and strengthens infrastructure locally, but also highlights Canada’s technological capabilities on a global scale,” said Cooper.

The first two machines are expected to be delivered in the fall of 2010, with tunnel boring to begin shortly after.

York Regional Chairman Bill Fisch speaks to the audience and TV cameras in front of an actual tunnel boring machine last Friday.
York Regional Chair and CEO Bill Fisch speaks to the audience and TV cameras in front of an actual tunnel boring machine last Friday.