Highway 7 East >> paving work between Bayview Avenue and Town Centre Boulevard

October 6, 2016

map

description

  • Red asphalt paving will continue this week along Highway 7 East.Crews will continue to re-pave intersections between Bayview Avenue and Rodick Road in sections overnight.
  • Crews will continue to re-pave intersections between Bayview Avenue and Rodick Road in sections overnight.
  • This work is covered by the two-year warranty included in the Highway 7 East rapidway project.

 

updated paving operations [overnight 7pm–6am*]

date intersection impacts
Oct. 6, 2016 Saddlecreek Dr to East Beaver Creek Rd No access
Oct. 7, 2016 Bayview Ave to West Beaver Creek Rd No access
Oct. 11, 2016 East Valhalla Dr to Rodick Rd No access

 

warranty work started: September 24, 2016

anticipated completion: October 11 [overnight], 2016

municipality: Highway 7, Richmond Hill, Markham

*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.

 

Linda Filippi
Manager, Community Liaisons
cell: 905.505.0514
email: linda.filippi@york.ca
Transit Inquiries
1-866-668-3978
yrt.ca