October 6, 2016
updated paving operations [overnight 7pm–6am*]
date | intersection | impacts |
---|---|---|
Oct. 6, 2016 | Saddlecreek Dr to East Beaver Creek Rd | No access |
Oct. 7, 2016 | Bayview Ave to West Beaver Creek Rd | No access |
Oct. 11, 2016 | East Valhalla Dr to Rodick Rd | No access |
warranty work started: September 24, 2016
anticipated completion: October 11 [overnight], 2016
municipality: Highway 7, Richmond Hill, Markham
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible.
|