grinding operations [overnight 7pm–6am*]
date | intersection | impacts |
---|---|---|
Sept. 21, 2016 | Town Centre Blvd to Cochrane Dr | Police controlled |
Sept. 22, 2016 | Cochrane Dr to East Beaver Creek Rd | Police controlled |
Sept. 23, 2016 | East Beaver Creek Rd to West Beaver Creek Rd | Police controlled |
Sept. 24, 2016 | West Beaver Creek Rd to Saddlecreek Dr | Police controlled |
Sept. 25, 2016 | Saddlecreek Dr to Bayview Ave | Police controlled |
paving operations [overnight 7pm–6am*]
date | intersection | impacts |
---|---|---|
Sept. 26, 2016 | Town Centre Blvd to Allstate Pkwy | Police controlled |
Sept. 27, 2016 | Allstate Pkwy to East Beaver Creek Rd | Police controlled |
Sept. 28, 2016 | East Beaver Creek Rd to West Beaver Creek Rd | Police controlled |
Sept. 29, 2016 | West Beaver Creek Rd to Saddlecreek Dr | Police controlled |
Sept. 30, 2016 | Saddlecreek Dr to Bayview Ave | Police controlled |
Oct. 3, 2016 | Valleymede Dr to Bayview Ave | Police controlled |
Oct. 4, 2016 | West Beaver Creek Rd to East Beaver Creek Rd | Police controlled |
Oct. 5, 2016 | Allstate Pkwy to Rodick Rd | Police controlled |
warranty work starts: September 21, 2016
anticipated completion: October 5, 2016
municipality: Highway 7, Richmond Hill, Markham