July 18, 2018
To accommodate asphalt repairs for warranty work, crews will be conducting various overnight operations in different locations on Davis Drive between Yonge Street and Patterson Street. Please see below for details.
what you need to know:
schedule:
work dates*: beginning Thursday, July 19, various nights over the next few weeks
work hours*: 7pm–7am [overnight]
nights | operation | location | impacts |
---|---|---|---|
July 19 |
red asphalt paving |
Davis rapidway between Longford/Parkside and Hill St. |
westbound traffic reduced to one lane |
July 30–Aug 1 |
red asphalt crack repairs |
Davis rapidway and intersections—more details to come |
at intersections and in stages, traffic reduced to one lane in each direction |
Aug 2 & 3 |
black asphalt crack repairs |
Davis Drive, locations TBD |
lane reductions in stages, details to come |
Aug 6–18 |
line painting |
Davis Drive, locations TBD |
lane reductions in stages, details to come |
general impacts:
We understand that overnight work is disruptive to those who live and work in the area, and have taken steps to reduce the impacts where possible. While we aim to balance the needs of commuters, businesses, area residents, the community at large and the project, night work is sometimes unavoidable.
crews dedicated to minimize disruption where possible: |
|
*Please note: As with other road construction projects, some work may be rescheduled due to weather or other variables. We are committed to providing advance notice whenever possible. Check twitter.com/vivanext for last-minute updates.
We thank you for your patience while crews work quickly to complete this work. If you have any questions or concerns, please don’t hesitate to contact us.