Categories
Video

2016 >> all together now!

YouTube video: 2016 year in review

Some of the best songs start with just a few notes – maybe the base in a band or the baritones in a choir. Then more and more parts are added, and by the middle of the song everyone is singing or playing different parts, all in harmony. For York Region’s rapid transit system, 2016 was the “middle of the song.”

The prototype station opened in 2011 in Markham, followed by a 10-kilometre rapidway opening in 2013 and 2014 on Highway 7 East. In Richmond Hill, a LEED Silver-certified transit service facility opened in 2015. The Davis Drive rapidway in Newmarket opened for service in 2015, with some final work completed last summer.

Along with finishing Davis Drive, 2016 projects included important utility and prep work along Yonge Street in Newmarket and in Richmond Hill – temporary traffic signals, median work and retaining walls, new hydro poles, water main and gas main replacements. Similar work is being done for the rapidway on Bathurst and Centre Streets in Vaughan, and along Highway 7 west of Highway 400 to Helen Street/Wigwoss Drive.

Highway 7 in Vaughan was a symphony of activity in 2016, with construction wrapping up east of Jane Street to Bowes Road, and work moving ahead quickly on the large rapidway station west of Jane Street that will connect directly to the Toronto-York Spadina Subway Extension.

Bus terminals are planned in Vaughan and in Markham, and in 2016 those projects worked through the “backstage” steps of design and procurement.

A high note in 2016 was the announcement from the Province of Ontario of $55 million in funding to advance the design and engineering for the Yonge Subway Extension [YSE]. The YSE is York Region’s top transit priority, and we’re committed to working with Metrolinx, TTC and the City of Toronto to move this project forward.

In our plans, 2016 was the year we knew most of our projects would be happening, all at the same time, and it was busy! 2017 will be full of accomplishments too, and there are even more rapid transit projects planned for the future. So we plan to keep working on every detail or “note” to make sure our song – a connected transit system – makes it to the finale!

 

Categories
Community Events Video

next stop… Yonge! the sky is the limit!

YouTube video: next stop... Yonge! Colouring Contest

What do you get when you give imaginative minds a box of pencil crayons, paper and creative license to draw their vision of the future of transit? Some pretty amazing masterpieces!

This fall we teamed up with the Town of Newmarket’s Recreation and Culture Department along with the Newmarket Public Library to give kids between the ages of 6-12 a challenge. We wanted to see their vision of what transit on Yonge Street will look like in the future. We received many colourful masterpieces brought to life as part of our Next Stop….Yonge! Colouring Contest.

Check out our latest video for a glimpse of the amazing entries we received. We’re sure you’ll agree that selecting our winners was no easy task. Congratulations to Avery [age 6-8], Sienna [age 9 and 10] and Olga [age 11 and 12]! Visit the contest page to see all the artwork we received.

We can’t wait to see what the future of transit holds for the next generation, the sky is the limit based on their imagination!

To find out what we’ve been up to in your community, check out our community events page.

 

Categories
Construction Safety Utilities Video

digging deep >> utilities at a glance

digging deep >> utilities at a glance

Before we can build dedicated rapid transit lanes, wider sidewalks, and plant beautiful greenery above ground, we need to go underground – to the world of utilities.

Our latest video peels back the layers to reveal all the modern conveniences we all depend on and often take for granted. We’ll shed some light on the steps we take to relocate critical infrastructure and explain why you see different crews come back to the same location as work progresses.

The most common things you’ll find are storm and sanitary sewers and pipes, water mains, gas mains, electrical wires, television/internet cables and phone lines.

We also take a look at the latest technology under the median and sidewalk planters , allowing trees and other plants to have deep, healthy root systems, and providing natural storm water management.

We’re just scratching the surface, but you’ll get a glimpse of how we replace and update infrastructure as an important investment that improves everyone’s quality of life.

 

Categories
Rapidways Safety Video

navigating the rapidways

click here to see the video -- rapidway intersections: safe journeys

Safety on the rapidway is everyone’s responsibility, and at vivaNext, we take it seriously. But that doesn’t mean we can’t look at an important topic in a light hearted way. You’ll need to watch our latest safety video to fully understand what we mean, but one thing is certain: you’ll be able to relate to one of our four travellers as they navigate our roads with Viva rapidways.

Motorist Molly, for example, needs to get to her mid-block destination, but gets stuck waiting for a left turn signal. What could be causing the problem?

Cyclist Cedric also has a turning concern while on the move. When travelling on dedicated bike lanes, making a left turn can be tricky business. Must he merge into dangerous traffic to get to the left turn traffic lane? Or is there an easier way?

Pedestrian Percy and his grandfather need to be fully aware of their surroundings when crossing the street, whether it’s to the vivastation in the centre lanes, or continuing to the other side.

However you get around, it’s important to understand what everyone else is doing to make sure your journey is a safe one. Watch the video, get to know the new surroundings, and take care when you’re travelling. Davis Drive and Highway 7 now have new ways to navigate, and there’s more to come!

 

Categories
Video

connecting Vaughan – east and west

connecting Vaughan – east and west

We’re building rapid transit in York Region – Bus Rapid Transit and subways – to connect York Region residents and commuters from north and south, east and west. Markham and Newmarket both have east-west rapidway connections, and next it’s Vaughan’s turn. From Yonge Street to Helen Street west of Highway 400, the new vivaNext rapidways will connect travellers with fast, convenient Bus Rapid Transit.

Vaughan Metropolitan Centre [VMC] is a hub of activity and the rapidway project is moving ahead quickly to open between Jane Street and Bowes Road by the end of 2016. Along the rapidway, Viva will stop at vivastations at Creditstone Road and Keele Street. Once the Toronto-York Spadina Subway Extension [TYSSE] opens in December 2017, Viva riders will also be able to connect at a vivastation west of Jane with direct access to the new subway station below, and a YRT bus terminal a short walk away. To see an overview of the project, check out our latest video.

This spring, construction begins on rapidways that will link vibrant communities in the east and west of Vaughan to the transportation options and development in the VMC, and to the rest of York Region.  We know it helps to be aware of what’s happening and when, so we promise to keep you informed and up-to-date along the way. If you haven’t already, be sure to subscribe to email updates for vivaNext projects, and follow us on Twitter.

Categories
Video

2015 >> what a year!

click here to see the Year In Review video

This was a landmark year, including opening an operations, maintenance and storage facility, the Davis Drive rapidway, and a park and ride lot in Newmarket. We’re at an important point with our rapid transit projects in York Region. All our funded projects are happening, and the results of the transformation are noticeable.

In November, the Davis Drive rapidway opened, connecting Newmarket east and west. Once sidewalks and landscaping are completed in 2016, Davis will have sidewalks lined with 470 trees and more than 21,000 shrubs and perennial plants.

Vaughan’s vibrant, new downtown is taking shape along Highway 7, with work continuing at a fast pace east of Jane Street on sidewalks, vivastations and landscaping. West of Jane Street, lanes have been shifted to their final configuration and work is being coordinated with the opening of the Toronto-York Spadina Subway Extension. The contract for the remaining rapidway along Highway 7 West in Vaughan was awarded in September, and utility relocations will begin in 2016.

On Yonge Street in Richmond Hill and Newmarket, utility work has begun and major road work will start in 2016.

The Highway 7 East project is now considered 100% complete, and has won multiple awards, including being listed as #2 in Road and Bridges Magazine’s Top 10 Roads list. Commute times are shorter on average, and the street is completely transformed from a highway with gravel shoulders, to a tree-lined street with wide sidewalks and accessible transit, welcoming to everyone.

In Richmond Hill, we opened an Operations, Maintenance and Storage Facility to support the growing fleet of Viva vehicles, and this massive facility was built to LEED Silver standards. A park and ride facility also opened in Newmarket at Highway 404, with the launch of the Davis Drive rapidway.

It’s been a landmark year, and there is more rapid transit and more connections to come, in 2016 and beyond.

 

Categories
Video

Highway 7 East >> how we got here together

Highway 7 East >> how we got here together

Before 2011, rapid transit projects were part a vision for York Region. To help set the stage for future growth, transit infrastructure was planned for York Region’s key towns and cities. Highway 7 East was the first to be built, and since construction began in 2011, has undergone a complete transformation.

At the west end, the rapidway has a remarkable [and accessible] two-story station taking pedestrians from Bayview down to Highway 7. And in the east the rapidway enters Markham Centre – a new development with a mix of commercial and residential development, including a new York U campus and a sports centre home to the Pan Am/Parapan Am Games in Markham.

The transformation may be most dramatic in the east end of Highway 7 near Warden, where originally the road didn’t have any sidewalks or bike lanes, trees were scarce and transit was mixed with other traffic. Now, there are dedicated lanes for Viva, tree-lined sidewalks and defined bike lanes, welcoming transit riders, pedestrians and cyclists to the street. To see the dramatic transformation of Highway 7 at the intersection of Town Centre Boulevard, check out this timelapse video.

In the years to come, Highway 7 will continue to develop with a mix of residential, commercial and office buildings. It will be the place to be for shopping, dining, working and living. The vision of quick, comfortable transit close to where people live work, shop and play is now a reality.

 

Categories
Video

creating connections

video: creating connections - a day in the life of a rapidway rider

Rapid transit is making it easier for people to move about York Region, connecting them to the places, people and things that matter. With all the traffic congestion the GTA currently faces, rapid transit can be a relaxing and time saving convenience. But what does this convenience really look like?

Because Viva travels in its own lanes along the length of the rapidways, riders save time and enjoy reliable service. Rapidway riders experience, on average, time savings of 16 minutes per round trip on the Highway 7 East rapidway, compared to making that same trip in a vehicle. And considering most commuters who travel along Highway 7 East will make daily round trips along the stretch of the rapidway, saving 16 minutes per round trip really adds up. In fact, it adds up to an annual time savings of 64 hours – that’s over two days! And less time spent travelling means more time for the things that matter.

Along with the rapidways, growth continues in York Region with new residential buildings, jobs and businesses popping up in the towns and cities, and along our roads. This means that people living in these urban centres won’t have to travel far to access services and amenities. They can easily walk, bike, or hop on Viva for a short trip to get where they need to go.

Rapid transit is providing convenience, reliability, and freedom for people to move around York Region easily. Watch our new video, day in the life of a rapidway rider, to see how one transit user enjoys the perks of the Viva rapidway along Highway 7, now that it’s complete

 

Categories
Construction Fun & Games

bringing rapid transit to your doorstep… a behind the scenes look at building a vivastation

Bringing rapid transit to your doorstep… a behind the scenes look at building a vivastation

Throughout the fall and winter, crews have endured every kind of weather Mother Nature has thrown their way, while installing the vivastation at Longford/Parkside and Davis. There are many detailed steps to constructing a vivastation, and as we shared with you last year, it takes careful planning and precision throughout those stages of the construction.

We’ve captured components of the delivery, installation and construction for the west and eastbound platforms at Longford and Davis on video to provide you with a behind-the-scenes look and better understanding of what it takes to build a vivastation. All of the vivastations that are built as part of the vivaNext bus rapidway project are an important component of the top-notch transit system in York Region. When the Davis rapidway is in service this December 2015, transit users will enjoy the convenience of the new-technology and innovative features that each Viva vehicle and vivastation offers.

As you can see in the video, the vivastation was constructed piece-by-piece, like a puzzle, and crews will continue braving the elements to add the finishing touches to the west and eastbound platforms at Longford/Davis throughout the year. The vivastations at Main and Southlake Regional Health Centre are also progressing right on schedule and will give transit riders all the same conveniences.

By the end of the year, Viva will be running on Davis Drive from Yonge Street to Highway 404 and residents and visitors to the area will begin to experience the benefits of having rapid transit at their doorsteps. We know living through construction hasn’t been easy and we’re grateful for everyone’s patience as we work as quickly as possible to complete this large undertaking.

 

Categories
Construction Rapidways

from messy to marvelous – davis drive year in review

Video: from messy to marvelous - davis drive year in review

It’s an exciting time as the transformation of Davis Drive has made significant progress and is starting to be seen along the corridor.

A lot of progress above ground was made this year and a number of milestones were achieved, all of which clears the way for 2015 and the last year of construction. We thank you for bearing with us through the mess and as we work hard to finish as quickly as possible.

Standing at Yonge and Davis, you can look down Davis Drive and see the installation of boulevards and planters. As you travel to your destination you’ll notice the decorative planters along with interlocking paving stones and concrete sidewalks in areas from Yonge Street to Longford/Parkside Drive.

Construction of the vivastation at Parkside/Longford and Davis is making great progress. The steel structure for the vivastation is in place and the glass for the canopies will be arriving soon.

Construction of two more vivastations at Main and Southlake Hospital are also underway.

The structure of the Keith Bridge has been rebuilt and the Tom Taylor Trail has been restored to its original location under Keith Bridge; which is located just past the GO train station.

VivaNext will be moving to the next phase of rapidway construction where station platforms, canopies and eventually rapid transit bus lanes will be built in the centre of the road. As a result, there will be permanent changes to how motorists use intersections, traffic lanes and access businesses along Davis. New traffic signals have been installed at Yonge, George and Barbara. Drivers can now make dedicated left-turns and U-turns where U-turn permitted signs are posted. From our experience on Highway 7, these new movements help the traffic flow smoother. For more information on these important changes please visit vivanext.com

We captured a number of these accomplishments on video and condensed them into a short clip for your viewing pleasure. The investment in modernizing our roads and revitalizing Newmarket’s infrastructure will go a long way to making sure Davis Drive is built on a solid foundation that will serve the growing needs of Newmarket for many decades to come. We look forward to the rapidway opening in 2015 and bringing Viva service to Davis Drive.