Categories
Construction Rapidways

turning on the lights

turning on the lights

Street lights are one of those infrastructure elements that the public may not give a lot of thought to, but in truth their design contributes significantly to the overall streetscape. And because the vivaNext project is being used to transform Highway 7 East from a highway to an urban corridor, all the design components, including the street lights, have been given a lot of thought. But before design considerations can be focused on, safety is the first priority to be achieved with street lighting. VivaNext works with York Region, the local Municipality and the utility companies to develop lighting designs, coordinate and install the lights. Here’s an overview of the role lighting plays in the vivaNext vision, and the street lighting elements you will see installed on all the rapidway corridors.

Designing street lighting, like all the major elements in the vivaNext project, focuses on achieving a combination of practical and design objectives. Lighting is first and foremost a public safety consideration. There are strict national and local standards on how street lighting is designed, including how much lighting is required for different conditions. For example, different measures are used to determine the lighting levels for roadways compared to intersections and sidewalks. Once the levels are known, lighting designers develop a design, which includes variables such as pole height, spacing and “lux,” which is the amount of light to be provided by the fixture.

Once the lighting design is done, streetscape design objectives can come into play in order to marry the technical requirements with the architectural priorities needed to achieve the desired streetscape “look.” In the case of vivaNext, the streetscape objectives are for a modern, stylish and uncluttered look that will contribute to the corridors feeling like urban destinations, and make them distinctive from other Regional roadways.

To achieve all these safety requirements and design objectives, we have selected a special street light pole and luminaire [the light head or fixture], and arm that holds the luminaire, to be used along the Highway 7 rapidway segments. The poles will be a little higher than the ones they’ve replaced [9.9 metres high versus 8.0 metres], and they’re made of metal with a dark grey powder-coat finish for long-wear and less maintenance. Unlike most poles which are octagonal shaped and tapered to the top, these are round and cylindrical for a sleeker, more modern look. And the lighting head or luminaire on top was chosen to complement the sleek, modern look of our canopies.

The street lights also have a photo sensor to automatically turn on and off when it’s dark. And the bulbs – which are little larger than the light bulbs you have in your home – only need to be replaced every 4 years.

So next time you’re sitting at a stop light or at a bus stop and you’re looking at the beautiful new streetscape, you’ll know more about all the decisions that were needed to turn on the lights! Enjoy!!

Categories
Construction Rapidways

bringing the vivaNext long-term plan for the future to life

video - Highway 7 East: summer update 2014

With crews working on the finishing touches on the eastern half of the Highway 7 rapidway, we’re getting closer to the completion of this rapid transit corridor. As much as we’re looking forward to celebrating this milestone, it’s only one [very exciting] step in a long path that started years ago.

There’s a lot of media coverage these days, of transit needs all across the Greater Toronto and Hamilton Area [GTHA], and we’re proud that York Region is actively working to bring rapid transit to our region. In 2002, the Region produced the York Region Transportation Master Plan and the follow-up Rapid Transit Plan, committing the Region to a blueprint of multiple transportation initiatives to be built over the next 30 years.

With approval to the Rapid Transit Plan, we got to work and in 2005 the Viva team launched “QuickStart,” the first phase of Viva service. Viva offered enhanced features that made transit more comfortable and convenient, and put the customer first. With ridership levels increasing steadily, Viva changed the way people in York Region thought of transit and there was appreciation for the higher level of services with enhanced features and frequencies.

But while our new Viva service was a major success and an important first step in encouraging people to try transit, designing the vivaNext rapid transit system was the Region’s long-term vision. Ontario municipalities are mandated to plan sustainable, more intensive land-use as part of the provincial government policy, and rapid transit is a key component in achieving that goal. Anticipating this, the Transportation Master Plan directed that future growth in York Region would be concentrated in new downtowns in Markham, Newmarket, Richmond Hill and Vaughan. By building more intensively in these areas, there would be less pressure for growth in existing neighbourhoods.

These urban centres would be connected by transportation “corridors,” making it easier for people to get around the region and providing transportation options, such as regular transit service. The vivaNext rapidways are being built along the corridors, providing these connections across York Region and into the rest of the GTHA.

Much of the new development being built around vivastations is compact and mixed-use, providing housing, employment, retail, dining, services and recreation, all within walking distance of transit. Developments include more welcoming public spaces, attractive landscaping, and other amenities that contribute to the centres becoming more dynamic destinations.

The plan is well and truly underway, and rapidways are being built on Highway 7 in both the east and west, as well as in Newmarket. The Toronto-York Spadina Subway Extension is under construction, and the designs for rapidways on Yonge Street are being finalized. Great new developments are popping up all over the new urban centres across the Region.

So when the next segment of rapidway on Highway 7 East starts service this summer, we can all celebrate the implementation of the first phase of our transportation and growth management blueprint, not to mention the end of construction! Check out the new video highlighting the Highway 7 East segment.

Categories
Construction Rapidways Uncategorized

check out the Keith Bridge progress

video - Davis Drive: Keith Bridge progress

It’s an exciting time for Newmarket as significant components of the Davis Drive rapidway project are beginning to take shape. Along with road widening and paving, construction of the first vivastation is underway at Parkside/Longford and Davis. As part of the vivaNext rapidway project on Davis Drive, the Keith Bridge is being completely reconstructed. Construction of the north side of the bridge is coming along and recently, the new bridge deck was poured with concrete. We’re excited to have captured part of the transformation!

The deck pour was originally scheduled to be a lengthy 16 hour operation, but to speed up the process our diligent crews brought in additional machines and completed the job in 8 hours – half the time. The pour was completed overnight, with crews working quickly and efficiently to minimize disruption to residents. Over 70 truckloads of concrete were pumped steadily into the form work of the bridge [similar to a mold]. Using what’s called a screed machine, the concrete was leveled out and smoothed to create a flat surface. Because the screed machine didn’t reach the outer edges of the bridge, workers expertly finished off the edges with hand trowels. Finally burlap and tarps were used to cover the poured concrete as part of the curing process. They were removed once the concrete set.

The bridge is on track to be completed by late 2014, and when finished it will include architectural features such as replica period light fixtures and poles, and decorative concrete railings that reflect Newmarket’s heritage. Check out the bridge pour video for yourself – after all, it’s not every day over 70 truckloads of concrete are poured in one continuous operation. Watch for more big moves as the transformation continues to unfold on Davis Drive!

 

Categories
Community Events Uncategorized

come say hello at the Newmarket Jazz Festival

come say hello at the Newmarket Jazz Festival

Another long weekend is upon us and there’s no better way to spend it than with family and friends. If you’re still looking for last minute weekend plans, look no further than the 2014 Newmarket Jazz Festival!

From Friday, August 1st to Monday, August 4th enjoy the sweet sounds of jazz at Riverwalk Commons, Newmarket’s Heritage Main Street & Fairy Lake [Map]. The Newmarket Jazz Festival proudly supports Herbert Carnegie’s Future Aces Organization – opening doors for creative youth in our Region.

For $5 per day [kids under 12 are free], experience live musical entertainment, various art performers, fabulous foods, shopping, vendor exhibits, a creative kids zone and much more. With free shuttle buses running Saturday through Monday every 20 minutes from 404/Leslie and the Upper Canada Mall, getting to and from the event will be hassle free. For ticket information, daily schedules and details on featured entertainers, visit the festival’s main website.

On August 2, 3 and 4 the vivaNext team will be on site at the festival to provide you with updates on all of our rapidway projects. The summer is our busiest season so we have lots to talk about. Stop by our booth to say hello, ask questions and try your luck on a summer scratch n’ win card – we’ve already had one winner so you could be next! Check out our summer contest page to find out about other ways to win.

On behalf of the vivaNext team we wish you all a happy and safe long weekend!

 

Categories
Community Events Fun & Games Ways to win

celebrate culture with vivaNext

celebrate culture with vivaNext

Experience culture from around the world right here in York Region!

This Sunday, July 20, Newmarket is hosting the fifth annual Around the World Multicultural Event to celebrate diversity in the community. From 12:00 pm to 8:30 pm, watch Newmarket Riverwalk Commons (200 Doug Duncan Drive – map) transform into a vibrant and unique cultural display. Indulge in a blend of delicious food and multicultural stage shows featuring music, dance, and theatre, all while learning about a variety of cultures.

Bring your family and friends to watch live performances on two different world stages, and interact with over 25 exhibitors eager to share food, crafts and information. Admission to the event is free and will take place rain or shine. In the case of inclement weather, all activities will be moved inside the Newmarket Community Centre & Lions Hall. For a full list of performance times and vendor types, see the main event page.

VivaNext is proud to be part of such a diverse community that values the culture, identity and opinions of its residents. We will be taking part in this year’s colourful festivities and we encourage you to join us. In between Zumba classes and First Nations’ teachings, be sure to stop by our booth to receive updates on the rapidway projects underway in your community. You can also try your luck on a scratch ‘n’ win card for the chance at some cool prizes.

Diversity is yet another reason why York Region is a great place to live, work, shop, and play so let’s celebrate!

 

Categories
Rapidways

steamrollers help roll out the transformation on Highway 7

The transformation along Highway 7 in Markham continues and the excitement is building. While we are all happy with the results of the completed section of Highway 7 East, there’s still work to be done on the remainder from Highway 404 to Warden Avenue. We are working hard towards completion and opening of the remaining 5 stations by the end of the year and making the most of every sunny day.

Crews have been busy with road widening, boulevard and centre median work and are now paving.  When you start seeing the steamrollers, you know the job is getting close to being completed.  There are a few steps to rapidway paving work which include street painting of the crosswalks, and paving of the red asphalt for the rapidway.  Right now crews are working on base layer paving from Allstate Parkway to South Town Centre Boulevard, as well as line paving and traffic switching.

Sometimes you may wonder why we’ve returned to an area even though it seemed like we were finished. In fact, what you’re seeing is that we are coming back to complete work which has to be done in layers.  Everything has a sequence and a process to finish the job. Paving requires only a few hours, but new pavement can’t be travelled on right away. We schedule paving work carefully to try to avoid paving during the most congested times of the day.

To minimize overall duration and immediate impacts to motorists, residents and businesses, crews will be working overnight and on weekends – weather permitting. This enables work to be completed in an area or on a piece of the construction that has a higher impact so that crews can then move on to the next section. To ensure safety during paving, police officers will be onsite to direct traffic and assist pedestrians.

The good news to remember is once the final paving is finished, we will be that much closer to opening the next section of the rapidway along Highway 7.  Think sunshine!

Categories
Construction Stations

building for the future: here comes the first Davis Drive vivastation

vivastation with blue glass canopy

 

If you’ve been travelling along Davis Drive recently, you’ll notice an exciting development taking shape on the vivaNext rapidway construction project: the installation of the first of three vivastations is being installed at the intersection of Parkside and Longford!

Here’s a quick overview of the vivastations, and how they’ll be installed.

Similar to the vivastations on Highway 7, the vivastations along Davis are going to be aesthetically pleasing and very functional. The curved Viva blue glass that makes up the canopy is surprisingly rugged – this glass is curved, tempered and laminated for strength, which prevents it from breaking into sharp pieces if it is cracked or broken. Reliability was our first priority in sourcing the manufacturer: our glass panels are actually being made by the company that makes nearly half of the world’s windshield glass.

Although the canopy is made up of nearly 100 individual panes of glass, each will be connected to its neighbour by small fasteners, referred to as “spiders” – so visually, the glass will look like it’s all one piece.

Supporting the glass underneath is a three-piece structure made of Canadian-fabricated steel, constructed just outside of Paris, Ontario. With durability in mind, the steel will be finished with a high-quality automotive-grade paint to minimize long-term maintenance costs.

Before the station components are delivered, a concrete platform is poured and set, and the connections built into the platform are prepared. Then the canopy’s three steel structural sections are brought in on a wide-load tractor trailer [it’s quite the sight to see them delivered!]. When installed they’re lifted into place. It takes about a week to align the sections perfectly and do some other prep work, in advance of the glass being delivered and installed. Lessons learned from Highway 7 have helped us find ways to modify the work to make the canopies easier and more efficient to install.

Because minimizing traffic impacts as much as we can is so important, our team has focused on finding strategies to install these huge canopies in a very small space with minimal lane closures.

Beyond providing rapid transit users with a comfortable and convenient experience, our vivastations are going to add a unique look and feel to Davis Drive which helps set the stage for future development. We look forward to celebrating this and other milestones as the work progresses!

 

Categories
Going Green

long, cold winter leading to plant woes

long, cold winter leading to plant woes

This past winter’s sub-zero temperatures, heavy snowfalls, driving winds and ice storm will go down as one of the longest and harshest on record. The effects of the ice storm are still being felt here in York Region, as we start to take stock of our plants, trees and shrubbery this spring.

In one of our earlier blogs, we talked about the trees, perennials and grasses that we’ll be installing in the planters in medians and boulevards along the Highway 7 rapidway between East Beaver Creek and South Town Centre Boulevard. Like you, we have noticed that some of the perennials and grasses have not come back this spring.

All the trees, perennials and shrubbery on Highway 7 are under a two year warranty and we are monitoring their growth to see if they need to be replaced or will come back throughout the spring and summer months.

We are hopeful that the chilly winter will result in better soil, leading to healthier gardens. Soil science shows that the cold weather creates pores in the soil, which naturally aerates plants. The colder it gets, the deeper frost penetrates. When the frost melts, it leaves pockets in the soil. Winter damage is always factored into gardening in Canada, as we assess our plants every spring and replace the ones that didn’t survive.

With all this in mind, vivaNext is committed to maintaining our new landscaping which will make Highway 7 much more attractive, pleasant and welcoming for everyone.

 

 

Categories
Community Events Construction

Join us for a construction tour!

Join Us!

Looking for something to do this weekend? Join vivaNext this Saturday, June 21st in Newmarket for construction tours and updates on the progress of the bus rapidway project! From 11am – 2pm, activities for all ages will be taking place at two locations: the vivaNext Project Information Centre [130 Davis Drive] and the corner of Main Street and Davis Drive.

Interested in how retaining walls are built, or curious about the preservation of heritage buildings? Sign up for guided walking tours at Main and Davis, taking place at 11am and 1pm, to get a behind the scenes look at the construction happening along the corridor. Kids receive free construction hats and can follow along with an interactive map. At the vivaNext Project Information Centre, view detailed maps and schedules of the project, and specialists will be on hand to answer any of your questions.

Throughout the day, kids can meet “Construction Guy” and “Explorer Girl” and everyone can cool off with complimentary ice cream. There are also plenty of opportunities to win prizes – enter for a chance to win a ShopDavis prize pack or pick up a scratch ‘n’ win card for additional giveaways.

We know construction is messy. For everyone who has continued to support our shops and businesses on Davis Drive, we truly appreciate it – continue to stop, eat and shop Davis. We‘re excited to meet you all and provide updates on what’s happening in your community. Hope to see you Saturday!

 

 

Categories
Construction General Rapidways Stations

signs, signs, everywhere a sign

It seems anywhere and everywhere you go these days there’s a sign of some type that catches your eye. Whether it’s an advertising, traffic or directional sign, it’s meant to grab your attention. The purpose of all the signs out there is for people to watch and read them every day as they pass by, so that you know what is going on in their neighbourhoods.

With the large number of signs out there you may become desensitized, but the signs in construction zones are there for your safety. A busy season of road work is underway on several vivaNext projects, so we hope drivers and pedestrians pay close attention to construction markers and signs as they may change daily depending on the work.

For pedestrians, crossing between intersections is tempting. But during construction, it’s especially important to cross at crosswalks – lane closures can change frequently and although construction areas are well marked, drivers may not see a pedestrian crossing unexpectedly.  When large equipment and trucks are working in an area, it is especially confusing if workers are not expecting people in their work zones, so please make sure you are in a safe area, which will be well marked with a sign, of course.

We understand the frustration of being a driver stuck in traffic too, and we’re using large digital signs on the street, to let you know ahead of time about lane closures and detours, as well as providing current travel times.   We hope these signs help you plan your route accordingly and help you manage your travel times.  To receive regular updates about our construction projects, subscribe to our email notices. And for on-the-go traffic alerts about our construction, follow us on Twitter.

Whether you’re biking, walking or driving this summer, we hope you’re enjoying the weather, staying alert and following the signs that keep you safe.