managing the vivaNext plan

When I first joined the vivaNext team, it was pretty small since we were still at the early stages of our rapid transit program.  Now, with an overall team of nearly 78 at York Region Rapid Transit Corporation (YRRTC); and many more staff and experts allocated to the projects through the construction contractors, all these people are working on the vivaNext plan which is going flat out, with planning, procurement, design and construction activities underway concurrently.  Here’s the rundown on what we’re doing now, and a preview on some of our other projects you’ll hear more about soon.

The most visible parts of vivaNext – our rapidway construction projects on Highway 7 East and Davis Drive in Newmarket – are definitely a major focus for our team, but they’re only part of what we’ve got going on these days. Moving a major infrastructure project like a rapidway segment forward from the early design stages to the introduction of service requires years of careful planning and oversight, starting with preliminary design and environmental assessments years before construction can start.   The same general work plan is currently being followed for the remainder of the Highway 7 rapidway (opening next year) and along Davis Drive in Newmarket.  Project management for our active construction projects involves a large part of our team, including engineering, property, finance and communications staff.

In addition, we’re in the early stages of pre-construction for the rapidway on either side of the Vaughan Metropolitan Centre (VMC) on Highway 7, with final design work being completed for the VMC station itself, overtop of the TYSSE concourse for the subway.

At an earlier stage, but already demanding dedicated project teams, is the Yonge Street rapidways in Richmond Hill and Newmarket, and the rapidways that will be built along this major commuter line.

And because a rapid transit network needs more than new lanes, stations and streetscaping, we’ve also got a number of dedicated facilities to plan and build, which will provide the future vivaNext system with more capacity for passengers, bus maintenance, and commuter parking.  All of those components are currently under active development, requiring the involvement of project teams with property, design, engineering and financial expertise.  Our currently funded projects add up to a total program value of $3.2 billion, which will see us build 37 km of bus rapidways with 38 stations, an 8.6 km subway extension with six stations, an operations facilities, two bus terminals and multiple park ‘n ride facilities over the next five years in York Region.

Last but definitely not least, lots of activity is underway to secure funding for future segments starting with the extension to the Yonge Subway, which is the missing link needed to fully connect the vivaNext system to the broader GTHA transit network.

Everyone at YRRTC works on multiple projects, which allows us to share our knowledge across the program, identify what’s worked well in the past, and ensure that we build on success.   Collectively we’ve already amassed a lot of expertise, making design and construction refinements to future projects that reflect what we’ve learned so far.

We all work hard, but the enthusiasm we pick up from the community is so motivating, it’s hard to imagine doing anything more satisfying.  We know that with just a few kilometers of rapidway open along the Highway 7 East rapidway, transit travel times have already been reduced and traffic flows improved.  So we’re all looking forward to the major improvements that we’ll all get to enjoy, when the whole system is open in a few years from now.

Stay tuned for regular updates throughout 2014, it promises to be a significant year for transit.

 

Categories
Construction General Rapidways

as the cold wind blows…

Seems like just yesterday vivaNext was ramping up construction activities at the first sign of warmer temperatures and while the warmer weather was here this year, a lot of progress was made along the vivaNext corridors. We captured our developments and put together a short video to share the progress of the transformation for each corridor.

Building on our successes, we will keep the progress moving even as we wind down for the return of Old Man Winter. Although the weather specialists forecast a cold winter season, our vivaNext construction projects will continue as the snow flies and the cold wind blows.  Here’s a snapshot of what we’re going to be working on this winter along the vivaNext corridors and how we’ll manage to keep construction moving along even when the temperatures plunge.

In Newmarket, crews will continue storm sewer installation, utility relocations and underground ductbank [gathers together and encases telecommunication wires] installation along Davis Drive. The south side of western creek culvert near Niagara Street will be also be widened over the next several months.

In Markham, utility relocations will continue on South Town Centre Boulevard, Cedarland Drive and Warden Avenue. Some construction work will also continue on Highway 7 East in the centre median.

Along the Vaughan Metropolitan Centre [VMC] corridor, hydro, gas and telecommunications installations and relocations will continue. Work will also begin on the CN Bridge. Preliminary construction activity also continues in Vaughan along Highway 7 West from Helen Street to Edgeley Boulevard and from east of Bowes Road to Yonge Street, including parts of Bathurst Street and Centre Street.

On Yonge Street, surveying, geotechnical testing and utility locates will take place in Richmond Hill and Newmarket. In early 2014, the design-build contract of the Yonge Street rapidway will be awarded. Once the contract is awarded, rapidway construction will begin.

While construction continues outside, inside our contractors are preparing for a busy spring. They are finalizing designs, plans and schedules for next year so when the warm weather returns construction crews can hit the ground running.

To see the progress we’re making over the winter, follow us on Twitter and Facebook. You can also sign up for email notices at vivanext.com to keep you updated on the construction underway in your area.

Categories
Construction General Live-work-play

ol’ man winter is here… are you ready?

Yes, it’s that time of year again, winter arrives officially this weekend.  The weather reports are full of white stuff, and the frosty temperatures are here.  Now is the time to ensure you are extra vigilant and aware of your surroundings at intersections, crosswalks and in construction areas as you travel the roads in York Region.

Snow and ice wreak havoc on the traveling public, but disasters are largely preventable.  If poor weather is forecast, plan ahead and leave plenty of time to get to your destination.  Better yet, postpone unnecessary trips until the weather has improved. As always we encourage you to try transit in bad weather days, but if you are driving, keep your vehicle tuned up and be especially aware of your tire condition.  Snow tires are the best bet in the winter months, but regardless of tire type, be sure to check pressures and tread wear regularly.

The bottom line is that winter is a Canadian fact and we can’t change the weather.  All we can do is prepare for it and understand the inherent hazards.

Here are some safety tips to help navigate construction zones in the winter safely:

  • Obey the speed limit – You should be careful to obey the speed limit in construction zones, as many will be lower than normal.
  • Keep on the lookout for construction workers – One of the main reasons that construction zones can be so dangerous is that there are often people working on the side of the road. You will want to be very careful when you drive and try to be aware of any workers.
  • Watch for lane changes – Often in construction zones, the lanes move differently than normal. Especially at night, in bad weather, or when it is difficult to see, pay attention to where your lane goes.
  • Be especially careful if there is no shoulder – A lot of times, construction forces the closure of the shoulder.

Remember to always be aware of road conditions and those who are working in these zones. As you pass through the vivaNext projects, we know that our construction disrupts the life of pedestrians, transit riders and drivers, and we do everything we can to keep that to a minimum.

We hope that as you pass by our construction areas you’ll keep safety in mind!  Travel safe!

Categories
General Uncategorized

social and community responsibility

The holiday season is a time of year where our community calls on all of us to help out just a little bit more and think of those that are in need of some help.

Here at vivaNext, staff are proud to be actively involved with the York Region Children’s Aid Society holiday Heroes program.  The Holiday Heroes program helps by donating new toys, new clothing, new winter outerwear, toiletries, gift cards and food vouchers to the children and families served by the agency.

This year, we have joined together to personally sponsor a family of seven.  Over the past two weeks, staff has been collecting everything from toiletries, toys, educational materials, practical items for teens and tweens – things we sometimes take for granted but that can be luxuries to a youth on a tight budget.

This season there are so many charitable organizations and agencies that are in need of support, be it money, merchandise, food or time. Sometimes the goodwill of the holiday season brings about great things.

At this time of year we would like to call to mind all the volunteers who tirelessly give of themselves to make life that much brighter and happier for those within our communities.  Thank you!

 

Categories
General Uncategorized

tis the season to support your local businesses

It’s that time of year again, holiday decorations adorn windows and doors, festive music fills the air and it seems everyone’s in a rush to go somewhere.  With the holidays fast approaching, you may be feeling a little overwhelmed with what to get that special someone.  Don’t fret the businesses along the vivaNext corridors are here to help you find the perfect gift.

The shops and services on Highway 7 and Davis Drive will take the stress and worry out of your holiday shopping. Your local merchants will help you find that perfect treasure for those nearest and dearest and will help you cross everything off your holiday shopping list. While you’re out and about, take a break from shopping with a stop at one of your favourite restaurants. Why not hop aboard yrt/viva to get you to and from your destinations?

Once you’re done shopping and you’ve checked your list twice, pour a glass of eggnog and congratulate yourself on a job well done!  You got all your shopping done with a little help from your local businesses.

Support your local businesses this holiday season. Your neighbours look forward to seeing you!

 

    [poll id=”45″]

 

Categories
Construction General Uncategorized

getting ready for winter

If you have a property with a garden, you’ll be familiar with the list of things you do every year to get things tidy and safe before it freezes up out there. We face the same kind of to-do list along our construction zones on Highway 7 and Davis Drive, although the key difference is we’ll still be actively working throughout the winter (I’ll tell you more about what we’ve got planned for the winter months in an upcoming post).

But in terms of getting things all tidied up, here’s what you’ll see us doing over the next couple of weeks to get ready for the snow and ice.

Our top priority, as always, is making the construction zones as safe as possible for pedestrians and drivers.  For that reason much of our pre-winter activity involves ensuring that sidewalks and boulevards are free of hazards, and hazards that cannot be removed are carefully fenced off.  In some cases we’re finishing the grading and construction of some boulevards, and in others installing temporary walkways and ramps where work isn’t scheduled to be finished until next year.

Snow fences are being installed behind sidewalks in areas where work is continuing, to help mark the safe route for pedestrians.  And because of ongoing roadwork and other activities, some sidewalks will remain closed.  We’ll make sure there’s a clear route for pedestrians through work zones, although it may require crossing from one side of the street to the other. Look for directional signage to know where it’s safe to walk, and how to access bus stops – for your own safety it’s critical that pedestrians stay out of work zones.

During construction, road and sidewalk maintenance is the responsibility of the construction contractor within the project areas.  But during the winter, the Region and local municipalities are responsible for ensuring the roads and sidewalks are kept clear. For that reason, another top priority before winter is to ensure every aspect of the construction zones is compatible with the requirements for winter maintenance operations.

This means making sure the snow-clearing equipment can manoeuver through the construction zones, boulevards and platforms.  Our design work and construction staging plans have always had those requirements top of mind, but we walk through the sites with Regional and municipal staff again before winter to identify any little details that might impede their operations.

And to keep traffic moving throughout the winter, we’ll be taking steps to make travel lanes as straight as possible through the construction zones, and ensure markings are clear.

Just like at your home, we like to get everything tidied up and in order before winter, so we’re going to keep working steadily at it until we’re forced to stop by severe winter weather.  Once that happens, we have a long list of other activities we will continue with, so stay tuned.

 

Categories
Construction General Rapidways

happy national housing day

Having a home is probably one of the most important and basic needs people have, and National Housing Day was introduced to remind us we should never take this fundamental need for granted.  This year National Housing Day is Friday November 22, and it’s being marked by special initiatives all across the country including here in York Region, where the Region is hosting a special social media and web-based campaign to raise awareness about the importance of affordable housing.

One of the biggest challenges facing our Region is that people have limited choice when it comes to affordable housing.  Traditionally a suburban region, many York Region residents have chosen to live in low-density single-family homes. As wonderful as that choice is for many, many families, there are some people who want – or need – other options.  And until recently, people who wanted to live in other forms of housing had very limited choices within the Region.

York has the lowest percentage of rental accommodation in the entire GTA. In some cases, that has meant people who want to live in York Region to stay near their families, or their jobs, have had to move away.  Whether it’s a young professional in their first job who has had to leave York Region to find affordable housing, or an older person who can’t manage a larger home on their own any more, too many people have found it hard to stay here at home.

Fortunately that’s changing, and VivaNext is a key driver that’s helping to expand the housing choices available here in York Region.

All along the viva routes, we’re seeing more and more housing being developed or proposed, including higher density developments near our new urban centres. Taking the direction from Regional Council, 35% of new housing in the centres and key development areas along the corridors have to meet affordability criteria, which is going to meet a key need here in York Region.

Building residential units along transit can help to reduce housing costs, since developments don’t have to include as much underground parking spaces.  This can reduce costs per unit significantly.  Another benefit of building near transit means people can get around without needing a car.  Whether you’re a young person moving out for the first time, or an older person who is happy to give up the keys to the car, that’s a significant advantage.

The best thing is that people who want to stay in York Region are now more able to, because rapid transit and long-term planning together are resulting in more choices, and more affordability.

So on November 22, give a thought to how much it would mean to you to be able to stay in the community you love, and to have a variety of affordable options to choose from.  We’re really pleased to be helping make that more possible, and wish you a Happy National Housing Day.

 

Categories
Construction General

clearing the way for construction

If you’ve ever watched a new subdivision get built, you know how fast the work seems to advance.  Crews install utilities, build rough roads, and before you know it there’s an entire subdivision ready for families.  But building a new roadway in a densely built-up area is a completely different challenge: the work seems to go on for a long time, and progress is hard to detect unless you know what you’re looking for.

We’ve been working flat-out on Davis Drive for a year now, with dozens of complex activities underway or completed from Yonge to Leslie.  Even so, most of our effort so far has been about clearing the way, rather than constructing a rapidway and stations.

That’s the predictable reality of modernizing our roads and revitalizing Newmarket’s infrastructure, but it’s worth explaining why we can’t get going on roadway construction until these steps are completed.

A key work priority has been to build retaining walls to enable the road widening along the hilly contours of Davis Drive,  with that work now nearing completion.

And like all major thoroughfares, the foundations of the existing Davis Drive roadway are literally lined along both sides with existing critical infrastructure carrying water, telecommunications, gas, storm sewers and sanitary sewers.  Much of this infrastructure crosses the road at intervals and in many cases the various utilities are stacked up in multiple layers.  In addition, at the sides of the road are hydro poles and lines, transformers for electricity and telecommunications, fire hydrants, and a whole range of privately owned signs for businesses and commercial buildings.

As much as we love getting to the stage of putting down asphalt and constructing the beautiful viva stations, we can’t start this until the right-of-way is completely clear. Once we’ve built the retaining walls, we need to relocate everything else, one element at a time, further back and out of the way of the new wider roadway.  Relocating utilities is a complex task in itself, requiring a highly detailed level of coordination between gas, hydro, telecommunications and other utility companies.

Each type of utility has its own specific requirements about how and where it can be relocated, and which one goes deepest, which has to be installed last, and so on.  Each element requires its own program of design work and approvals.  And lastly, different crews are responsible for specific utility relocations, and there are rules about how closely they can work relative to adjacent work crews.

So the job of getting the roadway clear for construction is a huge, time-consuming and enormously detailed process – without even considering the new bridge and retaining walls that are underway. With multiple activities to be carried out in each block, some people may wonder why we’re not progressing more quickly.  But the reality is that we’ve already completed much of the work needed to clear the roadway, and widening has already started in some segments.  Because so much of the work is underground, there isn’t much to see yet.  But as crews start paving, it will feel and look like progress is starting to take shape.

Even though building a rapidway is a long process, people along Highway 7 in Richmond Hill and Markham can attest that the transformation does come to fruition. Residents and visitors alike are now enjoying the Highway 7 rapidway. We look forward to the day the Davis Drive rapidway is complete and Newmarket can enjoy the finished result too.

Categories
General

why do we need retaining walls?

As you know, crews have been working hard on Davis Drive in Newmarket doing preliminary preparations and constructing a number of retaining walls.  With 16 already done and 1 remaining retaining wall construction is almost completed. Here’s why we need to build all these retaining walls.

If you’re at all familiar with Davis Drive in Newmarket, you’ll know how hilly the surrounding area is –the road itself is a series of hills, and many of the properties on both sides are either above or below the level of the road.

In general, retaining walls are used when one stretch of ground is at a different height than a neighbouring stretch of ground, and the slope between them is too steep to be stable on its own.  A retaining wall is used to hold the slope in place, and support the higher level of ground. Grade differences can be managed without retaining walls when the difference is slight, or where there’s enough space to make the slope very gradual. But because we’re widening Davis Drive, we’re reducing the space left over at the sides of the road, resulting in more pronounced grade differences between the road and some of the neighbouring properties and that’s why more retaining walls are needed.

The new walls will be built at the back of the boulevard where it meets private property, and where the grade at the back of the boulevard is different from the neighbouring grade.  Where the neighbouring property is higher, the retaining wall will extend upwards from the boulevard; where the neighbouring property is lower, the wall will extend down from the boulevard to the property behind.

The safety and design criteria for these walls are specific about what type of wall material is used for certain heights.  For walls that are less than 1.2 metres high, we are using pre-cast blocks that lock together like building blocks, set on a gravel base.  For taller walls, we’ll be using concrete that is poured in place, using special forms that mold the concrete and provide an architectural design.  To ensure safety, we’ll be adding an attractive aluminum handrail on the top of the retaining walls where it’s required.

These retaining walls will add to the more urbanized, stylish appearance of the future Davis Drive, and will help set the stage for the transformation that’s coming to this part of Newmarket.

Categories
Construction General Urban Planning

what is a culvert anyway?

 

I’m guessing that you probably weren’t thinking about culverts as you sipped your coffee on your commute through the construction this morning — probably not even if you passed right by one. But let me just take a moment to tell you why culverts are important – besides the obvious.

First of all, what is a culvert anyway? Well, I’m sure you’ve seen one by the side of the road, underneath a driveway, around creeks and rivers. A culvert is a tunnel or pipe of varying size, shape and material used to allow water  to move easily from one side of an obstruction (like a road or railway) to the other side.

A culvert has three main functions: to allow for stream crossing; to manage and direct water runoff; and to allow natural wildlife crossing. The first two are pretty self-explanatory, but where it gets interesting is the wildlife crossing.

Since culverts affect both animals and the environment, the Ministries of the Environment, Natural Resources and Transportation have set out specific standards for culverts. Those standards note that they must be constructed in such a way to allow any wildlife travelling through them to see light at the other side. And culverts must include material that mimic the natural landscape of the wildlife passing through it to encourage them to use the culvert for migration.

The typical lifespan of a culvert is somewhere between 10-20 years, depending on a number of factors. When water flows through a culvert frequently, as it does at eastern and western creeks in Newmarket, the culvert will naturally succumb to some erosion. With our plans to widen Davis Drive for the rapidway, we are extending the western creek culvert and removing and replacing the eastern creek culvert that was well beyond its lifespan.

It’s just one more component of an overall transformation towards vibrant urban centres, connected by a rapid transit network to help people get around.