Construction Rapidways

turning on the lights

turning on the lights

Street lights are one of those infrastructure elements that the public may not give a lot of thought to, but in truth their design contributes significantly to the overall streetscape. And because the vivaNext project is being used to transform Highway 7 East from a highway to an urban corridor, all the design components, including the street lights, have been given a lot of thought. But before design considerations can be focused on, safety is the first priority to be achieved with street lighting. VivaNext works with York Region, the local Municipality and the utility companies to develop lighting designs, coordinate and install the lights. Here’s an overview of the role lighting plays in the vivaNext vision, and the street lighting elements you will see installed on all the rapidway corridors.

Designing street lighting, like all the major elements in the vivaNext project, focuses on achieving a combination of practical and design objectives. Lighting is first and foremost a public safety consideration. There are strict national and local standards on how street lighting is designed, including how much lighting is required for different conditions. For example, different measures are used to determine the lighting levels for roadways compared to intersections and sidewalks. Once the levels are known, lighting designers develop a design, which includes variables such as pole height, spacing and “lux,” which is the amount of light to be provided by the fixture.

Once the lighting design is done, streetscape design objectives can come into play in order to marry the technical requirements with the architectural priorities needed to achieve the desired streetscape “look.” In the case of vivaNext, the streetscape objectives are for a modern, stylish and uncluttered look that will contribute to the corridors feeling like urban destinations, and make them distinctive from other Regional roadways.

To achieve all these safety requirements and design objectives, we have selected a special street light pole and luminaire [the light head or fixture], and arm that holds the luminaire, to be used along the Highway 7 rapidway segments. The poles will be a little higher than the ones they’ve replaced [9.9 metres high versus 8.0 metres], and they’re made of metal with a dark grey powder-coat finish for long-wear and less maintenance. Unlike most poles which are octagonal shaped and tapered to the top, these are round and cylindrical for a sleeker, more modern look. And the lighting head or luminaire on top was chosen to complement the sleek, modern look of our canopies.

The street lights also have a photo sensor to automatically turn on and off when it’s dark. And the bulbs – which are little larger than the light bulbs you have in your home – only need to be replaced every 4 years.

So next time you’re sitting at a stop light or at a bus stop and you’re looking at the beautiful new streetscape, you’ll know more about all the decisions that were needed to turn on the lights! Enjoy!!

Categories
Construction Rapidways

bringing the vivaNext long-term plan for the future to life

video - Highway 7 East: summer update 2014

With crews working on the finishing touches on the eastern half of the Highway 7 rapidway, we’re getting closer to the completion of this rapid transit corridor. As much as we’re looking forward to celebrating this milestone, it’s only one [very exciting] step in a long path that started years ago.

There’s a lot of media coverage these days, of transit needs all across the Greater Toronto and Hamilton Area [GTHA], and we’re proud that York Region is actively working to bring rapid transit to our region. In 2002, the Region produced the York Region Transportation Master Plan and the follow-up Rapid Transit Plan, committing the Region to a blueprint of multiple transportation initiatives to be built over the next 30 years.

With approval to the Rapid Transit Plan, we got to work and in 2005 the Viva team launched “QuickStart,” the first phase of Viva service. Viva offered enhanced features that made transit more comfortable and convenient, and put the customer first. With ridership levels increasing steadily, Viva changed the way people in York Region thought of transit and there was appreciation for the higher level of services with enhanced features and frequencies.

But while our new Viva service was a major success and an important first step in encouraging people to try transit, designing the vivaNext rapid transit system was the Region’s long-term vision. Ontario municipalities are mandated to plan sustainable, more intensive land-use as part of the provincial government policy, and rapid transit is a key component in achieving that goal. Anticipating this, the Transportation Master Plan directed that future growth in York Region would be concentrated in new downtowns in Markham, Newmarket, Richmond Hill and Vaughan. By building more intensively in these areas, there would be less pressure for growth in existing neighbourhoods.

These urban centres would be connected by transportation “corridors,” making it easier for people to get around the region and providing transportation options, such as regular transit service. The vivaNext rapidways are being built along the corridors, providing these connections across York Region and into the rest of the GTHA.

Much of the new development being built around vivastations is compact and mixed-use, providing housing, employment, retail, dining, services and recreation, all within walking distance of transit. Developments include more welcoming public spaces, attractive landscaping, and other amenities that contribute to the centres becoming more dynamic destinations.

The plan is well and truly underway, and rapidways are being built on Highway 7 in both the east and west, as well as in Newmarket. The Toronto-York Spadina Subway Extension is under construction, and the designs for rapidways on Yonge Street are being finalized. Great new developments are popping up all over the new urban centres across the Region.

So when the next segment of rapidway on Highway 7 East starts service this summer, we can all celebrate the implementation of the first phase of our transportation and growth management blueprint, not to mention the end of construction! Check out the new video highlighting the Highway 7 East segment.

Categories
Construction Rapidways Uncategorized

check out the Keith Bridge progress

video - Davis Drive: Keith Bridge progress

It’s an exciting time for Newmarket as significant components of the Davis Drive rapidway project are beginning to take shape. Along with road widening and paving, construction of the first vivastation is underway at Parkside/Longford and Davis. As part of the vivaNext rapidway project on Davis Drive, the Keith Bridge is being completely reconstructed. Construction of the north side of the bridge is coming along and recently, the new bridge deck was poured with concrete. We’re excited to have captured part of the transformation!

The deck pour was originally scheduled to be a lengthy 16 hour operation, but to speed up the process our diligent crews brought in additional machines and completed the job in 8 hours – half the time. The pour was completed overnight, with crews working quickly and efficiently to minimize disruption to residents. Over 70 truckloads of concrete were pumped steadily into the form work of the bridge [similar to a mold]. Using what’s called a screed machine, the concrete was leveled out and smoothed to create a flat surface. Because the screed machine didn’t reach the outer edges of the bridge, workers expertly finished off the edges with hand trowels. Finally burlap and tarps were used to cover the poured concrete as part of the curing process. They were removed once the concrete set.

The bridge is on track to be completed by late 2014, and when finished it will include architectural features such as replica period light fixtures and poles, and decorative concrete railings that reflect Newmarket’s heritage. Check out the bridge pour video for yourself – after all, it’s not every day over 70 truckloads of concrete are poured in one continuous operation. Watch for more big moves as the transformation continues to unfold on Davis Drive!

 

Categories
Live-work-play Urban Planning

then, now & next: Newmarket’s moments in time

then, now & next: Newmarket’s moments in time

Take a moment to travel back in time with vivaNext as we explore the past, present and future of the rapidway corridors. Over the next month, we’ll be digging into photo archives to explore each community’s unique heritage and showing you how the vivaNext projects will be part of this history.

First up is the charming Town of Newmarket! It became an official town in 1880 with a population of 2,000. Today, the town has 84,000 residents and continues to grow. It boasts small town charm, but has all the conveniences of a big city. Several historical pieces of architecture still remain in Newmarket today, and as part of the Davis Drive rapidway project, we are preserving these important pieces of culture that contribute to the Town’s character.

The Union Hotel was built on the northeast corner of Davis Drive and Main Street. The two-storey brick structure was designed by local architect John Ough and still has many of its original features. Past owners include James Burke, a soda water manufacturer, and Patrick Hodgins Sr. whose family used it as a store and residence. To allow for the widening necessary to accommodate the vivaNext rapidway, the Union Hotel and neighbouring two-storey concrete block building are being set back on the same property, to preserve them as a gateway to historical Main Street.

The Keith Bridge is also being reconstructed as part of the vivaNext rapidway project. Newmarket’s rich architectural and transportation heritage was the inspiration for the design of the new Keith Bridge. When finished in 2014, the reconstructed Keith Bridge will feature several historic design elements including replica period light fixtures and poles, and decorative concrete railings. Heritage lighting will accent the bridge and architectural detailing will retain a historical flavour.

Once complete, the Davis Drive rapidway will help to support successful urban revitalization by encouraging the development of attractive and pedestrian-friendly places for people to live, work, shop and play. Watch Newmarket’s then, now & next story and stay tuned to our YouTube channel for more videos on Richmond Hill, Vaughan, and Markham!

 

Categories
Construction Rapidways

signs of progress

signs of progress

We’re really counting down the days to the next section of the vivaNext rapidway service opening on Highway 7 East from East Beaver Creek Road to South Town Centre Boulevard, and we know you are too! You’ll know we’re really in the final stretches of construction once you see Viva buses out on the new section of rapidway starting next week.

YRT\Viva will be doing driver training and testing on the Highway 7 East new section in the City of Markham, starting July 28 for a few weeks.

Training will be provided for everyone who will need to be familiar with the rapidways, the stations and equipment. There will be vehicles out on the rapidway, taking customer service staff and other YRT\Viva staff along the rapidways to test and familiarize themselves with the new section. Regular transit service will continue to pick-up passengers at the curbside stops, while we do the testing and finish paving the new section. Signs directing passengers will be posted at the stops.

The actual operator training will run from 7am to as late as 9pm some nights, seven days a week. During this time you can expect to see Viva buses running up and down the rapidway, and stopping at stations. The training will focus on entering and exiting the rapidway, and especially entering back into mixed traffic under Highway 404 and past South Town Centre Boulevard.

Training will also focus on the new transit signals at intersections, which will provide a single green arrow for transit operations. This signal will be clearly marked as being for transit only, but YRT\Viva operators will be trained to be cautious and on the lookout to make sure members of the driving public are obeying the signals correctly and not turning into the red rapidway lanes.

The trainees are all experienced Viva operators, so they know the route and the vehicle and have been enjoying the first phase of the rapidway that opened last year on Highway 7; this is just another segment of the system now running in its own dedicated lanes. They’re really excited to get going, knowing that there are just few more weeks of construction ahead of them.

 

Categories
Construction

the challenge of relocating utilities

The Challenge of Relocating Utilities

If we were building our vivaNext rapidways across undeveloped fields, widening the roadway to incorporate the median bus lanes would be a straightforward construction project involving excavation, building the road base and drainage system, boulevard and station construction, installing illumination, and paving. But, in all our projects, there are many existing utilities along the roadways that need to be moved first. Believe it or not, this part of the project – relocating existing utilities – can sometimes result in the greatest amount of complexity and schedule coordination. Here’s a primer on why this least-obvious part of the project can be so time-consuming, but is so critical, yet so complicated.

Utilities – which on our projects include a wide number of companies providing electricity, telecommunications, cable and gas – are typically private entities, which in some cases have connections to local municipalities, and in other cases are private for-profit organizations. In all cases, utilities own their own infrastructure and are responsible for designing, installing, paying for, and maintaining it. Utilities have direct relationships with their own customers, and have to plan for, manage and respond to service interruptions.

With so many users relying on the services along the roadway corridors, we need to work together before we can widen the roadway for the vivaNext project. A first step is to identify existing utilities, to confirm what has to be moved out of the way. To complete this first step, we collect all the information we can, including “as-builts,” which are drawings showing the location of existing utilities. Using the as-builts [and sometimes ground penetrating radar], we then carry out physical locates, where we dig small test pits to confirm that utilities are where we think they are, and what condition they’re in.

Once there is agreement on which utilities need to be moved, each company designs a new alignment for their service, or designs a shared structure such as an underground duct bank, with another company. These relocation designs have to work with our project’s requirements and dimensions [and our project’s design has to provide for a reasonable relocation design for the utilities], as well as with the alignments of all the other utilities. Just completing the design coordination and review alone is a complex and iterative process.

With the utility relocation designs complete, municipalities and other approval bodies such as the Ministries of Environment and Natural Resources and local conservation authorities – and railway companies where rail crossings are involved – review, comment on, and hopefully approve the plans. In many cases, private property owners also need to agree to provide access to the utility companies, adding yet another layer of complexity and coordination.

The final stage is the actual construction of the relocated utilities. Because there are strict construction rules about the separation required between crews, we work carefully to sequence the relocation work.

The roadway widening cannot be completed until utility relocations are finished in any given area. And as in any activity where multiple organizations have operations underway, we all need to work together collaboratively, and coordinating our efforts is critical, so we can get the rapidways built and in service for you. Like I said….complicated!

 

Categories
Rapidways

steamrollers help roll out the transformation on Highway 7

The transformation along Highway 7 in Markham continues and the excitement is building. While we are all happy with the results of the completed section of Highway 7 East, there’s still work to be done on the remainder from Highway 404 to Warden Avenue. We are working hard towards completion and opening of the remaining 5 stations by the end of the year and making the most of every sunny day.

Crews have been busy with road widening, boulevard and centre median work and are now paving.  When you start seeing the steamrollers, you know the job is getting close to being completed.  There are a few steps to rapidway paving work which include street painting of the crosswalks, and paving of the red asphalt for the rapidway.  Right now crews are working on base layer paving from Allstate Parkway to South Town Centre Boulevard, as well as line paving and traffic switching.

Sometimes you may wonder why we’ve returned to an area even though it seemed like we were finished. In fact, what you’re seeing is that we are coming back to complete work which has to be done in layers.  Everything has a sequence and a process to finish the job. Paving requires only a few hours, but new pavement can’t be travelled on right away. We schedule paving work carefully to try to avoid paving during the most congested times of the day.

To minimize overall duration and immediate impacts to motorists, residents and businesses, crews will be working overnight and on weekends – weather permitting. This enables work to be completed in an area or on a piece of the construction that has a higher impact so that crews can then move on to the next section. To ensure safety during paving, police officers will be onsite to direct traffic and assist pedestrians.

The good news to remember is once the final paving is finished, we will be that much closer to opening the next section of the rapidway along Highway 7.  Think sunshine!

Categories
Community Events Construction

Join us for a construction tour!

Join Us!

Looking for something to do this weekend? Join vivaNext this Saturday, June 21st in Newmarket for construction tours and updates on the progress of the bus rapidway project! From 11am – 2pm, activities for all ages will be taking place at two locations: the vivaNext Project Information Centre [130 Davis Drive] and the corner of Main Street and Davis Drive.

Interested in how retaining walls are built, or curious about the preservation of heritage buildings? Sign up for guided walking tours at Main and Davis, taking place at 11am and 1pm, to get a behind the scenes look at the construction happening along the corridor. Kids receive free construction hats and can follow along with an interactive map. At the vivaNext Project Information Centre, view detailed maps and schedules of the project, and specialists will be on hand to answer any of your questions.

Throughout the day, kids can meet “Construction Guy” and “Explorer Girl” and everyone can cool off with complimentary ice cream. There are also plenty of opportunities to win prizes – enter for a chance to win a ShopDavis prize pack or pick up a scratch ‘n’ win card for additional giveaways.

We know construction is messy. For everyone who has continued to support our shops and businesses on Davis Drive, we truly appreciate it – continue to stop, eat and shop Davis. We‘re excited to meet you all and provide updates on what’s happening in your community. Hope to see you Saturday!

 

 

Categories
Construction General Rapidways Stations

signs, signs, everywhere a sign

It seems anywhere and everywhere you go these days there’s a sign of some type that catches your eye. Whether it’s an advertising, traffic or directional sign, it’s meant to grab your attention. The purpose of all the signs out there is for people to watch and read them every day as they pass by, so that you know what is going on in their neighbourhoods.

With the large number of signs out there you may become desensitized, but the signs in construction zones are there for your safety. A busy season of road work is underway on several vivaNext projects, so we hope drivers and pedestrians pay close attention to construction markers and signs as they may change daily depending on the work.

For pedestrians, crossing between intersections is tempting. But during construction, it’s especially important to cross at crosswalks – lane closures can change frequently and although construction areas are well marked, drivers may not see a pedestrian crossing unexpectedly.  When large equipment and trucks are working in an area, it is especially confusing if workers are not expecting people in their work zones, so please make sure you are in a safe area, which will be well marked with a sign, of course.

We understand the frustration of being a driver stuck in traffic too, and we’re using large digital signs on the street, to let you know ahead of time about lane closures and detours, as well as providing current travel times.   We hope these signs help you plan your route accordingly and help you manage your travel times.  To receive regular updates about our construction projects, subscribe to our email notices. And for on-the-go traffic alerts about our construction, follow us on Twitter.

Whether you’re biking, walking or driving this summer, we hope you’re enjoying the weather, staying alert and following the signs that keep you safe.

Categories
Construction General Going Green Urban Planning

choosing plants for colour, form and structure

If you’ve ever tried to fit a load of plants from a garden centre trolley into the back of your car, you’ll know that 292 trees and 4,910 perennials and grasses is a lot of plant material.

That’s the number of individual plants that we’ll be installing in the planters in medians and boulevards along our Highway 7 rapidways between East Beaver Creek and South Town Centre Boulevard, from now until the end of June.

As we’ve described in earlier postings, the plant selections were made carefully, and reflect expertise from our Landscape Architects and York Region’s own Forestry Department.  Plants in the planters need to be hardy and strong to be able to withstand the tough conditions imposed by their surroundings.  Not only do they need to be generally low maintenance, but being so near traffic means they have to survive wind, drought and salt-spray in the winter.

Another key requirement is that trees under hydro lines need to be naturally compact so that they don’t conflict with the lines overhead and can grow to their full potential without needing to be pruned.

So the final list was carefully developed with all these requirements in mind, and includes a wide range of trees, shrubs, perennials and grasses.  Trees include Kentucky Coffee tree, Ivory Silk Tree Lilac, and Ohio Buckeye, all of which are well regarded as decorative, long-lived trees.

Tree plantings will also include Skyline Honey Locust and Accolade Elm, both of which are prized as street trees for their vigorous growth and adaptability to tough growing conditions (and in the case of the latter, resistance to Elm disease).  Rounding out the tree selections, the Autumn Blaze Maple and Bradford Pear will provide colour interest and welcome shade.

Along the medians and in the boulevard planters, there is a wide range of grasses, shrubs and perennials which will provide form and colour throughout the year.  Most are familiar to home gardeners, such as varieties of red twig dogwood, shrub roses and Euonymus.  Mugho Pines and various forms of juniper will offer structure to our planters in the winter.  And grasses, daylilies and coneflowers will provide flower interest in the summer.

With all these plants the boulevards and vivastation platforms will be more appealing to pedestrians and transit riders, who will appreciate the shade and colour up close.  But even from a distance, the addition of new landscaping will make Highway 7 much more attractive and pleasant for everyone passing through, and will add to the feeling that this increasingly urbanized corridor welcomes all users.