zig-zags and traffic flips

Zig-zags during construction

Anyone who has driven with any regularity through one of our vivaNext construction zones will be familiar by now with the ongoing changes we periodically make to lane configurations, and the occasionally zig-zag layout of the temporary lanes. Here’s an explanation for those temporary lanes, and why they’re a necessary part of construction.

There’s no doubt that the fastest and easiest way to widen a road and build our BRT network would be to close the roads and divert all the traffic. Construction would be done soon and could even cost less. But Highway 7, Yonge Street and Davis Drive are among the busiest roads in York Region (which is why we’re building our first rapidways there). Any reduction to the number of lanes, even for a block, or for a short time, may result in traffic congestion and travel times, divert traffic into local neighbourhoods and hurt local businesses. Closures are only done for specific tasks, and only when there are no other reasonable options.

Widening the road and building the new rapidways can only be done when traffic is moved away. Even construction outside the roadway at the stations and boulevards requires extra space for safety and efficiency. Our project is complicated because we are building in the middle of live traffic lanes, so extra precautions are necessary.

The compromise is construction staging, meaning construction that’s done in individual steps or stages. Specific tasks requiring the same general work zone are carried out in one place at one time, before moving on to another area. To free up space, traffic is continually shifted, with temporary lanes moved around to accommodate active construction zones as our work progresses.

Creating a construction schedule and staging plan is a complex process, balancing community and project priorities. There are lots of considerations: maintaining traffic within the existing corridors rather than diverting traffic into adjacent neighbourhoods; minimizing disruption to drivers, local businesses and residents; working fast to finish on schedule so Viva rapidway service can begin.

Construction staging plans are developed block by block to include the timing and location of key construction activities, such as utility relocations; expansion or upgrading of critical infrastructure like watermains and sewers; road widening; building our rapidway stations; and constructing new features such as bike lanes and streetscaping elements. Preserving access to intersections, driveways and other important destinations is done to minimize impacts on residents and businesses. We also need to plan for specific construction requirements such as access for oversized construction equipment, or creating extra space around a short-term activity.

In general, we’ll do a set of tasks on one side of the road before the lanes are shifted (or “flipped”) for work to be done on the other side. And before traffic is shifted, we make sure the community and drivers are given plenty of advance notice so they know when travel lanes are going to be moved.

Ultimately, building a major construction project in the middle of a busy thoroughfare requires us all to share the road for a period of time. By staging our construction, we can ensure the safety and convenience of the community and drivers while keeping our crews safe so they can get the job done.

Categories
Live-work-play

those carefree summer days are here!

those carefree summer days are here

School’s wrapping up and summer’s here! Are you excited? We are. Summer is the time of year when vivaNext gets a lot done. This summer, work on our Davis Drive rapidway in Newmarket is entering the home stretch, and we’re excited to see it taking shape. We’re also widening roads and paving in Vaughan on Highway 7 West, and last but not least we are putting the final touches on our Highway 7 rapidway in Markham in preparation for the Pan Am Games.

Summer is a great time for you to get things done too – important things like swimming, cycling, camping and barbecues.

Warm weather and no school mean carefree days, which is why it’s more important than ever to drive carefully. Children and teens will be running around having the time of their lives. Sometimes they run into the streets without looking, skateboard on busy streets, or do other things you wouldn’t expect. It’s motorists’ job to be extra vigilant, helping our kids stay safe.

In our busy lives, driving sometimes feels like a race from one place to the next. Is it really worth the rush? Sidestepping rules of the road by talking on a cell phone or rolling through a stop sign can be tempting. But, take your time. Slow down and enjoy the summer. Keep your attention on the road and watch for construction detours, speed signs and children.

And if you find driving is becoming a little tedious, you can try Viva, which is running throughout York Region. As you know, six kilometres of bus rapid transit are already running in Markham from Bayview to Warden, providing travel times that are as much as 35% faster, so experience it firsthand.  This route will be a fast, convenient alternative to driving your car throughout the Pan Am Games this summer.

However you choose to get around, we hope you make the most out of your summer – drive with care and be safe!

 

Categories
Uncategorized

working hand-in-hand

working hand-in-hand

Sometimes the best way to get through big, complex tasks is to split the workload – divide and conquer. This is especially true with York Region’s transit network, so we work alongside the Transportation Services Department.

With strategic plans in place, the Transportation Services Department plans the overall transportation network, including roads, transit and cycling. They create a Transportation Master Plan, which takes into account many factors, including ideas from residents, population growth and other statistics, provincial mandates like Places to Grow, and environmental protection measures like the Greenbelt and Oak Ridges Moraine. They also build and maintain roads, and through YRT/Viva, operate conventional YRT transit, Mobility Plus and Viva rapid transit.

At vivaNext [York Region Rapid Transit Corporation], we put the rapid transit part of the Transportation Master Plan in place. We work with all levels of government to acquire funding for each new project, whether it’s Bus Rapid Transit rapidways, subways, or transit facilities. We design and build these projects – including details like station locations and designs, sidewalks and lighting.

As the project manager, we set timelines and manage construction contracts. The rapidways are major infrastructure projects requiring careful scheduling and seamless handovers when each project goes into service. At this end point, the operations are handed over to YRT/Viva, and the maintenance is done by either York Region or the local municipality, depending on who owns the road.

At vivaNext we have some projects in place already, more scheduled for the next four years, and a few projects yet to be funded. Along with York Region’s growing population, there’s a growing need for transit. So there’s a lot to do, and we’re working hand-in-hand to get everything done.

If you’re looking for a few videos, you can get a glimpse of the transformation of York Region, see what York Region’s Transportation Services does, or just catch a little excitement.

 

Categories
Construction

working in harmony with the weather

working in harmony with the weather

As Canadians, we tend to be a little bit obsessed with the weather, and no wonder. With such extreme fluctuations, our climate affects everything we do: our commutes, our weekend plans and our way of life. Watching the Weather Network is one of our national pastimes, right up there with hockey.

At vivaNext, our crews work in all kinds of weather to build a rapid transit system for York Region.

When the sun shines, crews push forward to get the job done. But when the forecast is for thunderstorms, extreme heat or cold, heavy rain or snow, our crew leaders have to assess the situation and decide whether or not to work. Then they make a call, for the safety of their people and the success of the project.

extreme heat

At this time of year, extreme heat poses a major weather hazard. Paving when it’s 35°C can be dangerous for the health of our crews, and plain miserable as well. However, a worker in a trench below ground may find it cool enough to work in extreme heat.

thunderstorms

Lightning and thunder are a no-go from a safety perspective. But as we all know, the weather report is a changeable beast. When the forecast is thunderstorms, contractors building vivaNext rapidways have to make tough decisions. They can bring their crews out and then find it’s too stormy to work. Or they can call off work for the day, only to find the storm never comes and a perfectly good working day is lost. The decision comes down to safety.

rain

Crews can pave in light rain for one or two days, but eventually wetness takes a toll. A tarp or cover can be used when pouring concrete in the rain, while waiting for it to cure. The safety of the men and women working on vivaNext projects is a top priority. Rain can make construction sites slippery, muddy and dangerous, and pose undue hazards.

underground weather

The weather underground is another factor. While it may be sunny and warm where we are, temperatures drop below ground.  Digging frozen ground can be a challenge and can damage equipment.

the bottom line

When our crew leaders decide not to work in bad weather, they’re thinking of the safety of the men and women they lead, and the success of the project.

Crews take advantage of Mother Nature by capitalizing on the good weather to drive vivaNext rapidway construction forward and we are happy to report we have had a great start to the construction season this year!

The result will be a transit network York Region will be proud to call its own, a legacy that keeps our communities moving forward into the future.

 

Categories
Construction

paving season is always a good news story

click here to see the paving video!

If it’s spring, it must be paving season! [see the video]

It’s not unusual for us at vivaNext to get very excited about paving season because it is always a good news story. The fact is construction can be dusty and disruptive – but, just like seeing the leaves open up on the trees in spring – the surest sign that the heavy construction is nearing its end is when the paving crews arrive.

Currently, as platform construction continues for the future vivastations along Highway 7 in Vaughan, the next segments of base-layer paving have begun between Edgeley Blvd./Interchange Way to Keele St. This paving will be completed in sections over the next two months and will include closures and detours.

One question you may be asking is why do crews revisit a section once it’s paved? The process happens layer by layer, which is why the crews will come back to the same location more than once. Because Highway 7 has to bear the load of regular traffic and heavy vehicles, we need to start with a solid base layer to make sure the road holds up over time.

To create the red pavement on the rapidways, we use a special pigment that is carefully mixed to achieve the right balance of rich red and rugged durability.

Each step needs to be done in sequence, and takes a certain amount of time. While the paving itself doesn’t take more than a few hours, fresh pavement can’t handle traffic right away. Also, we plan the work outside of busy business traffic times of the week, and the day – for example, crews typically work overnight and on weekends – weather permitting.

To stay informed about the paving activities along Highway 7 in Vaughan this spring and summer, check out our paving page at vivaNext.com/paving7. On vivanext.com you can also find Davis Drive paving and construction info, and sign up for construction updates.

 

Categories
Construction Fun & Games

bringing rapid transit to your doorstep… a behind the scenes look at building a vivastation

Bringing rapid transit to your doorstep… a behind the scenes look at building a vivastation

Throughout the fall and winter, crews have endured every kind of weather Mother Nature has thrown their way, while installing the vivastation at Longford/Parkside and Davis. There are many detailed steps to constructing a vivastation, and as we shared with you last year, it takes careful planning and precision throughout those stages of the construction.

We’ve captured components of the delivery, installation and construction for the west and eastbound platforms at Longford and Davis on video to provide you with a behind-the-scenes look and better understanding of what it takes to build a vivastation. All of the vivastations that are built as part of the vivaNext bus rapidway project are an important component of the top-notch transit system in York Region. When the Davis rapidway is in service this December 2015, transit users will enjoy the convenience of the new-technology and innovative features that each Viva vehicle and vivastation offers.

As you can see in the video, the vivastation was constructed piece-by-piece, like a puzzle, and crews will continue braving the elements to add the finishing touches to the west and eastbound platforms at Longford/Davis throughout the year. The vivastations at Main and Southlake Regional Health Centre are also progressing right on schedule and will give transit riders all the same conveniences.

By the end of the year, Viva will be running on Davis Drive from Yonge Street to Highway 404 and residents and visitors to the area will begin to experience the benefits of having rapid transit at their doorsteps. We know living through construction hasn’t been easy and we’re grateful for everyone’s patience as we work as quickly as possible to complete this large undertaking.

 

Categories
General

numbers, numbers… how we report progress

numbers, numbers… how we report progress

We recently updated the percentages on our website that show how far along each of our rapidway projects are: Highway 7 East is 95%, Highway 7 West [phase one] is 30%, Davis Drive is 70% and Yonge Street is 8%. It might make you scratch your head, since some of these projects appear to be more, or less, advanced than these percentages reflect. And in some cases, progress doesn’t show up in the percentages.

The percentages are updated quarterly, and are based on each project’s budget and how much has been billed. To stay open and transparent about our budgets and project progress, we report these percentages and information about construction milestones to our Board of Directors. Once our quarterly reports are presented to the Board, to Metrolinx, and to York Region Council they’re available to the public [posted here on our website]. There are variations from time to time – for instance, in our most recent report, we reported on the third and fourth quarter of 2014 together because there was no Board meeting in the fall.

As for the progress of each project:

  • The Highway 7 East rapidway is fully in service, and now that the snow is gone crews are completing some top-layer paving and sidewalk/landscaping work near Warden Avenue, taking care of the last 5%.
  • The percentages for the Davis Drive and Highway 7 West rapidway projects didn’t change between the third and fourth quarters of 2014, but as anyone knows who spends time on these roads, crews have been working through the winter and progress has been made [just not reflected in the budget or billing yet].
  • At just 8%, the Yonge Street rapidway is just getting started and for the next several months much of the progress will be with relocating and updating utilities in preparation for road widening.

When working along streets that are heavily travelled, in ever-changing weather, digging into underground infrastructure, there’s always a chance of delays along the way. But by keeping track, and reporting our progress, we can make sure everyone knows how it’s going.

 

Categories
Rapidways

2014 – a year of action

2014 - a year of action

As 2014 draws to a close, we’re pleased to say that each of our projects saw great progress this year. The Bus Rapid Transit projects start and end at different times so each has its own construction schedule to match the unique challenges, such as: length of rapidway, complexity of underground work, and landscape and infrastructure features like hills and bridges. As we progress through these challenges we consider them milestones, and after a year of milestones there are plenty of moments to look back on.

On Highway 7 East in Markham, the second stretch of rapidway opened from Highway 404 to South Town Centre Boulevard, and construction will be complete on the last piece to Warden Avenue by the end of 2014, with some finishing touches to add in spring 2015. This final section allows Viva customers to experience the future of rapid transit in York Region, from Bayview Avenue in Richmond Hill to the Downtown Markham development area. Riders are already seeing up to 35% travel time savings on the rapidways.

In Newmarket on Davis Drive, utilities and telecommunications were relocated to prepare for road widening and building the rapidways in the centre of the road. Road widening continued and base-layer paving was also completed in sections along Davis. Significant milestones included: completing the structure of the Keith Bridge and reopening the Tom Taylor Trail, moving the Union Hotel into its final location and installing the steel structures for the first vivastation at Longford/Parkside. The glass canopies will be installed over the winter and the vivastations at Main Street and Southlake Hospital are also underway. It’s been a busy, messy year but crews are working quickly. We’re in the home stretch with the rapidway set to open December 2015.

Along Highway 7 West in Vaughan, the first phase of rapidways is well underway and a there has been a lot of progress in 2014. Between Jane Street and the CN Bridge, work continues on base-layer paving, building retaining walls and expanding the CN Bridge, and we’re almost done relocating some underground infrastructure. East of Jane Street, the road has been widened and traffic has been shifted, so that work in the centre of the road [including paving, installing vivastations platforms and canopies!] can begin in 2015. The contract for phase two of the rapidways in Vaughan will be awarded in 2015, adding dedicated bus lanes and vivastations from Edgeley Boulevard to Pine Valley Drive and from Bowes Road to Yonge Street [in blue on map]. While some pre-construction activities are already underway, construction is expected to begin in late 2015/early 2016.

On Yonge Street in Richmond Hill and Newmarket, the contractor is working to finalize the rapidway design and construction schedule. Meanwhile, crews are out conducting surveys and utility investigations to make sure we have an accurate record of what’s above and below the ground.

We’re also building a state-of-the-art Operations, Maintenance and Storage Facility in Richmond Hill to act as a ‘home base’ for transit. This nine-acre, 481,679 square foot facility will be LEED® certified [Leadership in Energy and Environmental Design], and is scheduled to be complete mid-2015.

Everyone’s busy making memories during the holidays, but we hope that you’ll have a few moments to see some of our videos that give you a sneak peak at rapid transit in York Region:

Where did it all begin? See the launch of curbside Viva service in 2005. Also see the vision for the transformation of York Region and some of the considerations given to the design of the rapidway vivastation, and take a peek inside the rapidway vivastations.

While you’re watching videos, why not find out what’s happening in your community:

 

 

 

Categories
Construction Rapidways

from messy to marvelous – davis drive year in review

Video: from messy to marvelous - davis drive year in review

It’s an exciting time as the transformation of Davis Drive has made significant progress and is starting to be seen along the corridor.

A lot of progress above ground was made this year and a number of milestones were achieved, all of which clears the way for 2015 and the last year of construction. We thank you for bearing with us through the mess and as we work hard to finish as quickly as possible.

Standing at Yonge and Davis, you can look down Davis Drive and see the installation of boulevards and planters. As you travel to your destination you’ll notice the decorative planters along with interlocking paving stones and concrete sidewalks in areas from Yonge Street to Longford/Parkside Drive.

Construction of the vivastation at Parkside/Longford and Davis is making great progress. The steel structure for the vivastation is in place and the glass for the canopies will be arriving soon.

Construction of two more vivastations at Main and Southlake Hospital are also underway.

The structure of the Keith Bridge has been rebuilt and the Tom Taylor Trail has been restored to its original location under Keith Bridge; which is located just past the GO train station.

VivaNext will be moving to the next phase of rapidway construction where station platforms, canopies and eventually rapid transit bus lanes will be built in the centre of the road. As a result, there will be permanent changes to how motorists use intersections, traffic lanes and access businesses along Davis. New traffic signals have been installed at Yonge, George and Barbara. Drivers can now make dedicated left-turns and U-turns where U-turn permitted signs are posted. From our experience on Highway 7, these new movements help the traffic flow smoother. For more information on these important changes please visit vivanext.com

We captured a number of these accomplishments on video and condensed them into a short clip for your viewing pleasure. The investment in modernizing our roads and revitalizing Newmarket’s infrastructure will go a long way to making sure Davis Drive is built on a solid foundation that will serve the growing needs of Newmarket for many decades to come. We look forward to the rapidway opening in 2015 and bringing Viva service to Davis Drive.

Categories
Construction Rapidways

seeing the transformation unfold on highway 7 west

click here to see the video of 2014 Vaughan rapidway construction

we’ve been busy this year

Construction is well underway for the first phase of vivaNext rapidways in the City of Vaughan, and the transformation can be seen along Highway 7 West. Check out our latest video for an up-close look at the milestones we’ve accomplished this year. Although construction will continue throughout the winter months from Edgeley Boulevard to Bowes Road, here’s an update on the progress made in 2014:

  • Traffic has been shifted east of Jane Street to its final configuration, so that work in the centre of the road [including platforms and canopies] can begin in 2015.
  • As part of the 8-metre expansion of the Canadian National Railway [CN] MacMillan Bridge, we poured over 800 tonnes of concrete to create new columns and bridge pier caps.
  • Underground infrastructure revitalization continues – utility, telecommunications and storm sewer relocation is approximately 80% completed.
  • Road widening is completed and base-layer paving is 90% finished between Jane Street and the CN Bridge. Paving activities will continue in 2015.
  • In order to preserve the existing Black Creek and Hillside Culverts, retaining walls were built. In total, five retaining walls have been completed along the corridor with a few more set to get started in 2015.
  • Important traffic and pedestrian changes can be seen at several intersections. Motorists are benefiting from new turning movements and pedestrians now have two-stage crossings.

We know construction can be messy and disruptive at times, and we thank you for your patience and understanding as we continue the transformation. For up-to-date information on construction progress and activities, visit http://www.vivanext.com/hwy7progress.