Categories
Fun & Games

#MyYongeStreet Selfie Contest

#MyYongeStreet Selfie Contest

Get your selfie stick ready, the #MyYongeStreet selfie contest launches on Monday, August 14!

We’ve partnered with the Town of Newmarket and the Newmarket Chamber of Commerce to bring the summer of selfies to Yonge Street. Enter for a chance to win weekly prizes or one of three grand prize shopping sprees. We’re proud to support the businesses that make Yonge Street a great place to stop, shop and dine.

here’s how it works

Take a selfie with your purchase from a business on Yonge in Newmarket, share the image on Twitter or Instagram using the hashtag #MyYongeStreet, and you’ll be automatically entered into weekly random draws for a chance to win one of three Yonge shopping sprees. You can also submit your image to contest@vivanext.com for a chance to win.

contest dates:

  • Monday, August 14 through to midnight on Sunday, September 3, 2017

it’s easy to enter:

  1. Visit a business within the Yonge Street rapidway construction area in Newmarket [between Savage Road/Sawmill Valley Drive and Davis Drive].
  2. Take a ‘selfie’ with your purchase in the business on Yonge.
  3. Post your selfie on Twitter or Instagram, or email to contest@vivanext.com, using the hashtag #MyYongeStreet.

prizes!

  • Each week, three lucky winners will receive $100 to be spent in the store where the winning selfie was taken.
  • There will be three grand prize draws for Yonge Street Shopping Sprees valued at $1000, $750 or $500.

To learn more about the contest, visit vivanext.com/selfiecontest.

Categories
Rapidways Uncategorized

what exactly is a ‘partial rapidway’ ?

what exactly is a ‘partial rapidway’ ?

Where there are dedicated rapidways in York Region, there are also transition areas to get buses in and out of mixed traffic – and something called “partial rapidways”. Here are some simple explanations of what will be happening with transit in these areas.

full dedicated rapidway

The typical rapidways are dedicated lanes in the centre of the road for buses serving specific Viva routes. Vivastations are located roughly every kilometre or so, with customers being able to access the stations via signals at intersection crosswalks. Rapidways will allow Viva vehicles to zip past regular traffic.

transition lanes

Transition lanes take the buses into and out of the centre-lane rapidway. A good example of this is on Davis Drive west of Yonge Street.

partial rapidway

For the purposes of the vivaNext projects, partial rapidway typically means dedicated bus lanes in one direction of a roadway only. For example, in the Bathurst & Centre area, there will be dedicated rapidway for the most part on Bathurst and Centre Streets, and partial rapidway in three locations:

  • On Centre Street between Highway 7 and Dufferin Street, there will be regular centre-lane rapidway going westbound, and partial rapidway eastbound (full rapidway starts part-way).
  • The rapidway on Bathurst Street over Highway 407 and Highway 7 will be one direction southbound. The northbound rapidway will end just north of Flamingo Road.
  • The rapidway on Highway 7 between Bathurst Street and Yonge Street will be one direction eastbound. The westbound Viva route will run in mixed traffic.

transit in mixed traffic

While a partial rapidway is still in the centre lane, when Viva bus routes run in regular mixed traffic, there are no designated lanes, meaning that buses will travel in lanes that are also used by other vehicles. This usually occurs along roadway areas that are more highway-like without a lot of residential or commercial development, and therefore not a lot of customers.

For example, on Highway 7 roughly between Bayview Avenue and Yonge Street, Viva buses exit the rapidway and rejoin regular mixed traffic. Also, in the short section along Highway 7 between the GO Barrie bridge underpass and Centre St., there is no road widening or improvements as the underpass is not being widened. Therefore, in this stretch, transit will be in mixed traffic.

curbside rapidway

The vivastation at Bayview Avenue is curb-side with two levels, to allow customers to transfer between east-west transit service on Highway 7 and north-south service above on Bayview Avenue.

Designing rapidways is complicated, but it takes into account the local area geography and the ridership levels, today and in the future. This ensures that vivaNext is building dedicated lanes in areas that will see the highest levels of improved travel times.

Any questions you have, we are happy to answer. And if you’d like to keep up on what’s happening in the construction areas where we’re building rapidways, subscribe to email updates at www.vivanext.com/subscribe.

 

 

Categories
Innovation

as technology advances, every little step counts

as technology advances, every little step counts

We are always amazed to see examples of technology that depart from the norm. Like this driverless drone “sky taxi” that will begin flying customers in Dubai, United Arab Emirates this summer. If everyone had their own personal drone it would certainly change the daily commute!

Sometimes though, it’s smaller innovations that change transportation for the better for people. Bus rapid transit that rides in dedicated bus lanes is now part of the landscape in Markham, Richmond Hill, Vaughan and Newmarket. At the end of this year in Vaughan, the Toronto-York Spadina Subway will change how many people commute.

Within a transit service there can also be improvements and innovations. YRT/Viva’s goal is to be emissions free by 2051, and their 2017 Annual Service Plan notes several pilot and trial programs underway, including:

  • Electric Bus Demonstration and Integration Trial
  • Alternative Fuel Study
  • Small bus strategy

Over time, these smaller changes can make a big difference. Just fifteen years ago, few people would have predicted that bus customers would be able to zip past congested traffic on Highway 7. And while subway extensions have been a priority for a long time, it’s pretty amazing that residents of Vaughan will soon be living so close to a subway line.

Dreaming about new innovations for the future is one thing; making it happen is definitely another. And in York Region we’ve made these changes together. The future looks bright with more innovation to come!

 

Categories
economic & financial Urban Planning

change that works

change that works

Cities around the world are searching for safe, sustainable ways to provide mobility to residents across towns and cities. VivaNext, a leader in rapid transit, has risen to the challenge. We pride ourselves on designing a great transportation system that has social significance and measurable benefits.

VivaNext is proud to support the triple bottom line. This business principle holds that business activities should result in financial, social and environmental benefits. The benefits of rapidways are easy to see. For example, the dedicated bus lanes not only allow for fast, convenient service across the region, but they also help facilitate a safer road for drivers, pedestrians and cyclists alike. In addition, emergency service vehicles are able to access the rapidways and cross the median at designated intervals, which improves their response time and bypasses congestion.

What may not be immediately visible, however, are some of the positive economic and environmental impacts rapidways create for communities.

economic development & impact

  • Well thought-out and well-designed transit attracts sustainable, mixed-use development, including new businesses, jobs and a variety of housing options
  • Easy access to transit creates a more desirable mixed-use neighbourhood, and allows for money to be reinvested into the community (through businesses or reinvesting in local infrastructure)
  • Based on other rapid transit projects across North America, property values increase for land within walking distance to transit stations
  • As the Region’s urban transit corridors evolve and attract new retail and restaurants, other new employers wanting to be near transit will follow, continuing to support future economic and social growth

environmental responsibility

  • Every busload replaces approximately 70 vehicles on the road, which means a reduced carbon footprint
  • Rapid transit systems create a safer, more accessible and walkable city

With so many positive benefits of rapid transit, it’s no wonder York Region is a leader in transforming our communities by providing safe, convenient rapid transit. Join us and be moved.

Categories
Accessibility Construction Stations Subways Technical

matching the heights

matching the heights

With the extraordinary maneuvering required to install the roof sections of the VMC BRT station in its location in the centre of Highway 7, you might think the most challenging part of this project has been its incredible glass and steel canopy.

It’s true that installing the canopy of the station required a lot of planning and meticulous engineering. But actually, the coordination of the underground subway station with the BRT station above has been – and still is – a much more complex logistical challenge.

the mechanics of it all

Building the actual physical connections between the two structures was involved but not unduly complicated, similar to any building that has a framed structure on top of a concrete slab. Because the top of the station is wider than the lower part and overhangs at the edges, we couldn’t use rebar dowels, which are the most common construction method. Instead, we used mechanical couplings that enabled us to essentially bolt the top to the bottom.

working together

What makes the project more challenging is that the subway station is being built by the TTC, while the above ground BRT station is being built by vivaNext. With two different owners, and two different contractors, the project demands an intensive degree of coordination and planning.

Joint planning work began long ago, starting with establishing the specific requirements for how the project needed to be built, both below and above ground, and inside and outside the subway station. With the TTC building the subway station up to the surface, and vivaNext building the BRT station from the ground up, the heights of floors and ceilings had to line up perfectly.

top to bottom, inside and out

The vertical elements between the lower and upper floors – including the stairs, escalators and elevators – had to be installed early, with no margin for error. Escalators are very rigid, designed to fit perfectly between floors. And because the rapidway runs right through the station, the top of the escalator, stairs and elevator also had to align precisely with the existing level of Highway 7 outside.

At the same time as the TTC was building the lower levels of the subway station, we were outside building the civil works – the roadway, curbs and gutters – that surround the BRT station. Again, because the rapidway runs through the station, the heights of the underground parts of these elements had to fit with the height of the subway box below.

The BRT station is well on its way and is already a head-turner. In the not-too-distant future, all of this engineering and coordination will make it possible for you to step off the escalator at VMC subway station and easily make your way to the BRT station on Highway 7 and beyond.

See an artist’s rendering of the VMC BRT station once complete.

 

Categories
Construction Rapidways Safety Traffic signals

changing lights

Most people look at traffic signals every day, but don’t notice how they’re configured, or why they’re installed the way they are. Traffic signals change quite a bit with our construction projects, and not just from green to yellow to red.

Once a project is underway, each intersection in the construction area receives a new, temporary traffic signal pole on each corner, set farther back from the road. Then temporary traffic signals are strung on wires across the intersection from these temporary poles.

Once the temporary poles are in place, the old poles and signals are removed, including any poles in the centre median in each direction.

Having the temporary poles farther back from the road allows access for relocating utilities and widening the road. As lanes are shifted and the road is widened, the temporary signals are adjusted along the wires to ensure they’re in the correct place for traffic and pedestrians.

Later in the project, new poles are installed in their final location, and permanent traffic signals are added, along with a dedicated left/U-turn signal.

Each time the traffic signals are changed, paid-duty police officers are on hand at each intersection for a few hours to ensure traffic flows safely through the intersection. If you’re on Yonge Street in Newmarket or Bathurst and Centre Streets in Vaughan, you’ve seen this firsthand recently.

For a peek at the final outcome, check out the sections of rapidway on Highway 7 East in Markham and Davis Drive in Newmarket.

Despite the cold weather, the vivaNext team continues to work out on the corridors and behind the scenes – making progress as seamlessly as possible.

 

Categories
Communications Construction Live-work-play Rapidways Uncategorized Video

so many different activities this year in Vaughan!

Vaughan 2016 year in review

So much has happened this year along Bathurst and Centre and on Highway 7 West. Just take a look!

In this video, you can check out some of this year’s behind-the-scenes activity – like trees being transplanted to parks, and pre-construction work – as well as the very visible work you saw, like water main and gas main construction.

It was a big year for rapidway work as well, with boulevard and planting on Highway 7, red asphalt in the rapidway and the big vivastation canopy going up in the Vaughan Metropolitan Centre area.

New utilities, wide pedestrian-friendly sidewalks, shade-giving trees – and smooth rapidway are all part of the vivaNext projects, creating new infrastructure that will serve generations to come, and leave a lasting legacy for the Highway 7 West and Bathurst & Centre communities in Vaughan.

As the year comes to an end, it is great to reflect on our accomplishments. We look forward to more progress in 2017.

For more information on ongoing work be sure to sign up for email updates, and follow us on Twitter. Questions or comments? Comment below or email us at contactus@vivanext.com.

Categories
Construction General Rapidways Utilities Video

a year on Yonge

a year on Yonge

‘Tis the season when we sit back and reflect on the year which has passed and prepare for the year ahead.

2016 was a big year for utility work on Yonge Street in both Newmarket and Richmond Hill. Gas and telecommunications installations were completed in Newmarket and water main and gas work made significant progress in Richmond Hill.

Through all of the construction barrels, mud, noise and mess on Yonge Street, we took pictures every step of the way and put together a video which captures the progress of rapidway construction in both Newmarket and Richmond Hill.

It is amazing to look back and remember all that can be achieved in just one short year. We look forward to another productive year in 2017!

Categories
Construction Rapidways Safety Stations Uncategorized

working day and night

Those living and working in York Region know firsthand about dealing with construction. During prime construction season, you typically see worksites on a number of Regional roads. We need these road improvements to ensure our fast-growing communities are connected by a strong transportation system.

So how do we get these projects done when people still need to use the roads?

VivaNext rapid transit projects are carefully planned to manage construction and maintain traffic flow. There is a balance on every construction project between the need to get work done on schedule, the need to keep traffic moving, and the construction disruption to adjacent homes and businesses.

On occasion, night work is scheduled on busy roads such as Highway 7 or Yonge Street to avoid traffic congestion during the higher-traffic daytime hours. For example, on Yonge Street between Weldrick Road and 16th Avenue, there is up to eight times more traffic during the day than during the overnight hours.

We understand that sitting in traffic can make commutes longer. On the other hand, when work is done at night we know the noise and lights can make it difficult for those living nearby. The project still needs to be completed, so we move forward, trying to strike a balance – with over 99% of the four-year project being done during the day. Work is limited during peak traffic times, and crews work diligently to complete overnight work quickly so that it’s over as soon as possible.

We know that a good night’s sleep is important, and our crews try to minimize the amount of noise and light they create while they’re working overnight.

Day or night, it helps to know what’s coming so you can plan around it. You can sign up for email notices at vivanext.com/subscribe. Thank you for your patience and understanding.

Categories
Construction Rapidways Studies Technical

designing for the future

Who can remember? Not so long ago Highway 7 in Markham and Richmond Hill was a suburban highway: a few isolated developments, lots of parking lots and open fields, but no sidewalks, no plantings, no bike lanes–and certainly no dedicated rapid transit bus lanes. Just look at it now!

In only a few years from start to finish, construction begins and is completed on each of the rapidway projects. In the world of infrastructure renewal, vivaNext construction projects are known to be implemented very efficiently, and we’re doing everything we can to maintain that great reputation.

years of work are behind the design

What’s not so apparent to the public is the lengthy design process that happens long before construction starts. Design of the many engineering and architectural elements must take place stage by stage. Throughout, the designers need to balance staying true to the original vision with making it work in different conditions and geographical areas.

a variety of disciplines at work

VivaNext uses a multi-disciplined design team including: engineers who specialize in civil, traffic, structural, geotechnical, electrical and transit systems; architects; environmental consultants; landscape architects, security experts and more.

many stakeholders weigh in

At each stage, different options and features are reviewed, adjusted and improved with input from municipal staff, utility companies, local conservation authorities, property owners and others. Depending on the location of the project, specific design issues are addressed in conjunction with the owners of adjacent infrastructure including GO Transit, 407 ETR, CN, and the Ontario Ministry of Transportation.

the stages of each project

The process is not a fast one; the Environmental Assessment process, which established the conceptual design for vivaNext, was begun in 2002, and the whole process for any one segment from Preliminary Engineering to service start may take 6 or more years. Here’s an overview of the stages each of our projects go through, before shovels can hit the ground.

•    Environmental Assessment [EA]: The EA examines alternatives and identifies a preferred design. The vivaNext conceptual design shows the approach for individual segments like the number of rapidway and traffic lanes, boulevards and planting zones and the arrangement of stops and stations. The EA then identifies potential design impacts on the natural and built environment, traffic, noise, drainage, property, etc., and proposed strategies to avoid or mitigate and monitor them.

•    Preliminary Design: This stage takes design to approximately 30% completion and establishes the outlines of the project including its alignment and profile, what additional property is needed to build the project, development of major components like bridges or culverts for water crossings, entrances and intersections, utilities, and listing permits and approvals.

•    Detail Design: This stage fleshes out the preliminary design for all elements. For example, preliminary design may identify that a high retaining wall will be needed at a specific location; 60% design will show the kind of foundation needed and the wall’s general construction; 90% design will show the colour and design of the material to be used on the outside of the wall, and 100% will show all details and specifications required to construct the work.

•    Issued-for-Construction Drawings: These are the final design drawings to be used by the contractors, once all approvals are complete.

By the time vivaNext is complete, all our projects will share the original design vision, but their individual design will reflect local requirements and various conditions. Each segment is tailor-made to be functional, convenient and beautiful, with the primary goal of providing a rapid transit system for the future. Which is, and always has been, the ultimate vivaNext design objective.