Rapidways Stations

where will the vivastations be along Bathurst & Centre?

where will the vivastations be along Bathurst & Centre?

We’ve heard your questions about vivastation locations along Centre and Bathurst Streets, so here’s everything you need to know…

The Phase 2 rapidway project will include 10 new vivastations, with five of them along the current Viva bus route on Bathurst and Centre Streets. This is already one of York Region’s busiest Viva routes, so stops were planned where people will want to get on and off Viva.

From west to east, this is where the stations will be:

  • Centre Street at Dufferin Street.
  • Centre just east of Carl Tennen Street & Vaughan Boulevard.
  • Centre at North Promenade & Disera Drive.
  • Bathurst Street at New Westminster Drive.
  • On the connector road between Bathurst and Yonge Street.

As with all rapid transit in York Region, we plan stations to be walking distance from shopping, important services, and places to live and work. When it’s all done, the Centre and Bathurst area will have updated utilities and traffic signals, tree-lined streets and bike lanes. Preconstruction starts this year, including utility locations and relocations, and watermain upgrades.

For more information about the project, visit our project page. And if you have any other questions, feel free to comment or email us at contactus@vivanext.com. To stay up-to-date on construction, sign up for email updates at vivanext.com/subscribe.

 

Categories
Rapidways Urban Planning

building complete streets in York Region

building complete streets in York Region

When looking at the award winning rapidway on Highway 7 in Richmond Hill and Markham, or Davis Drive in Newmarket, you’ll notice some features that make them different from your average street.

Wider sidewalks, more accessibility features, large attractive tree planters to provide a buffer between pedestrians and traffic, and bike lanes where possible, are all part of York Region’s urban design philosophy. It’s an approach that will shape the future of our communities and neighbourhoods, and it’s what Urban Planners call a ‘complete street’ – a street designed for everyone.

The complete street transformation is starting to unfold on Yonge Street in Richmond Hill and Newmarket this year. Utilities are being relocated to accommodate the dedicated bus rapid transit lanes in the centre of the road. In time, the same thoughtful and elegant elements will take shape on one of the region’s most important roads for transportation, commerce and entertainment – the perfect place to stop, shop and dine – Yonge Street!

The complete street approach ensures that planners and engineers design and manage public infrastructure that takes in account users of all ages, abilities, and modes of travel.

One of the underpinnings of the complete street approach is to treat roads as destinations. With careful planning, roads can be public spaces with lush greenery and design features that engage people. Streets can be places to go instead of just surfaces to drive on. They should connect to businesses and places where people live, and also to trails, parks and other gathering places in order to help build a sense of community.

Another key consideration is accessibility, because whether you get around in a stroller, wheelchair, on transit, walking, cycling or driving, everyone needs safe and convenient options.

To learn more about complete streets and how they are being implemented across Canada and around the world, visit completestreetsforcanada.ca, or smartgrowthamerica.org.

 

Categories
Rapidways Subways

in continuous motion

in continuous motion

At this point in building York Region’s rapid transit system, we can officially say there are projects at every stage. A few rapidway projects and transit facilities are open for service, some are well underway and some are just getting started.

Having projects at different stages can be beneficial. We learn from every project and fine-tune important processes like procurement, financial management and construction scheduling. Special attention is paid to tailoring detailed designs to ensure quality, and scheduling construction to keep impacts to a minimum. Project management is what we do, and to get everything done, we stack the deck with technical knowledge and lots of experience.

Bus Rapid Transit

With 34.6 kilometres of dedicated lanes for Bus Rapid Transit [rapidways] completed or underway we have lots on the go, but there is also much more to do. The remaining half of rapidway projects – 34.2 kilometres – have Environmental Assessments completed and are ready to move forward once funding is in place. This includes completing Highway 7 rapidways in eastern Markham and western Vaughan, and Yonge Street rapidways between Richmond Hill and Newmarket, and north of Davis Drive.

Yonge North Subway Extension

York Region’s highest priority, the Yonge North Subway Extension, is ready to move to full engineering and construction. This 7.4-kilometre extension from Finch subway station to Highway 7 in Richmond Hill will include five stations and will complete a missing link in the GTA transit system. The Yonge Subway Extension has been identified by Metrolinx as a priority project, and the Environmental Assessments and some important studies are complete, so once Provincial funding is confirmed for preliminary engineering this project will be moving forward to this important next step.

As with any great transit system, our projects are in continuous motion. Our experience allows us to think ahead, in planning for each project, and in building a connected transit system for those who live, work or commute in York Region. To help plan the transit system in the GTA, Metrolinx is hosting a series of public meetings in York Region and Toronto in the next five weeks. We’ll be there too, so be sure to drop by our booth.

 

Categories
Construction Going Green Rapidways Uncategorized

3 ways function will meet beauty this year on Highway 7 West

Greenery red pavement paver stones

There is always a point in time every January when it seems like the bitter wind and frozen ground will never give way to gentle breezes and fresh green grass.

If you’re having one of those moments, here are three things to look forward to this year, after winter is over – in particular, three features of the rapidway project that match function with beauty.

Here are three functional, attractive developments you will see happen on Highway 7 West in 2016:

1. Sidewalks, beautiful sidewalks

Want to be the first person to ever walk on sidewalk on Highway 7 all the way from Jane Street to Keele Street? This is the year you’ll be able to do so, for the first time in Highway 7’s history. Those sidewalks will also be beautiful to walk on, with gorgeous paver stones. If you need to look at a sample of what’s to come, you can check out the already installed sidewalk on the north side of Highway 7 between Jane and Creditstone, along Highway 7 East in Markham, and on Davis Drive in Newmarket.

2. Greenery

Concrete planter boxes are being constructed in the centre of the rapidway and along the sidewalks. This spring, they will be filled with nutrient-rich soil and planted with a carefully curated selection of trees, bushes and plants. Highway 7 West will turn green!

3. The iconic red pavement

This is the year you’ll get to see that glorious red asphalt appear along the newest rapidway on Highway 7. Suffice to say, we get very excited about seeing this roll out, because it delineates the rapidway and because it looks so darn great. Once again, function meets beauty.

If you’d like to subscribe to email updates about the progress of the vivaNext project on Highway 7 West in Vaughan, click on this subscriber link, or go to our homepage at vivaNext.com and scroll down to “subscribe”.

Categories
Commissioning Rapidways Safety Stations Uncategorized

vivastations >> built for comfort and safety

vivastation safety and comfort

We’ve taken every possible step to make the vivastations on the new Davis Drive rapidway feel like a safe haven, especially considering the stations are located in the middle of a busy roadway.

While you wait for transit, you can take comfort in the fact that you are well protected from the elements and adjacent traffic, and able to get help easily if you need it.

safety starts with design

The new vivastations include a variety of safety features, and are designed with transparency and good lighting in mind – two key principles of CPTED [Crime Prevention Through Environmental Design]. Stations have a concrete barrier wall along the traffic side, and a steel and glass guardrail beyond the glass canopy. The glass is impact-resistant with an interior film that prevents shattering [similar to a windshield] and provides UV sun protection.

call buttons are crucial

In the case of an emergency, an Emergency Call Button is clearly marked inside the glass enclosure. Its speaker provides immediate two-way contact between the caller and YRT operators. Call audio is recorded and time-stamped, as is the video automatically captured by the closest of three security cameras when the button is pushed. When the button is pushed, blue strobe lights on the Variable Message Sign [VMS] and the button are triggered to indicate to passing emergency services that assistance is needed, and transit staff will dispatch emergency services if needed.

safety is personal too

As much as we’ve designed vivastations to be safe, safety is also in the hands of those driving and walking on Davis Drive. While many drivers are now accustomed to making U-turns, but for others, it’s new. Drivers and pedestrians should both stay alert, and keep an eye out for one another, especially in intersections – and especially in fall and winter when daylight is in short supply.

two-stage crossings have rest spots

Because intersections were widened, a two-stage crossing at crosswalks is recommended for pedestrians. There are waiting areas in the middle of the crosswalk, where pedestrians can press the “walk” button and wait for the next signal.

Safety features are one of those things that are only top of mind when they’re needed. We hope that you always keep them in mind. That way you can rest assured that your rapidway trip will be a safe haven.

Categories
Commissioning Construction Rapidways Stations

testing, testing, 1-2-3

Testing for the new rapidway along Davis Drive

Have you recently travelled along Davis Drive from Yonge Street to Roxborough? It’s looking great! We’re very close to making the new bus rapid transit services available to you. What lies ahead is testing.

The testing stage – known in the construction world as commissioning – is critically important to ensure that all parts of the rapidway are ready for active service.

Here’s what’s involved

commissioning

In the case of vivaNext, commissioning involves reviewing every part of the rapidway system, including structural components and the overall communications network, to ensure that they are working the way that we’ve designed them to.

Intelligent Transportation Systems [ITS]

ITS is an international transportation-engineering discipline that aims to make all kinds of travel more efficient. You may not be able to see it, but ITS technology is a critical component of the vivaNext rapid transit project.

In general, ITS ensures that traffic corridors are designed as one coordinated system, which includes the physical roadway’s design, lane markings and signs, traffic signal design and timing, and the brains that connect all these pieces. On the vivaNext rapid transit corridors, ITS plays another role too – integrating the rapid transit system into the overall traffic corridor system.

communications network

The communications network includes the fare collection equipment; the station information systems such as variable message signs [VMS], clocks and public address [PA] systems; the passenger security elements such as closed circuit TV systems and emergency call buttons; and the traffic signals at intersections. It also includes the sophisticated Transit Vehicle Detection system, which informs traffic signals when rapid transit vehicles are approaching intersections. Finally, the overall communications network includes the fibre optic network that links all of its components.

testing, testing, testing

Testing starts at the factory, where the fabricator verifies that the equipment works as intended. Each component is then tested again when it’s installed. After this, a series of additional tests are carried out to confirm that the entire system is integrated properly and working together.

The final step involves testing the reliability and function of the system, including simulating actual operation using buses, and staff who act as passengers. This gives the people who will be involved in the future operation, maintenance and service of the rapidway an opportunity to become familiar with it.

Even though you can see construction is coming along, there’s still testing, testing, and more testing to be done before the Davis Drive rapidway opens in December. All this testing is important though; it will ensure that rapid transit on Davis Drive is as safe and efficient as possible.

Categories
Rapidways Stations

rapidways in winter

rapidways in winter - Town Centre Station on Highway 7 East

It’s definitely winter! Nobody knows that better than outdoor maintenance crews. When there is snow and ice, York Region’s crews are on duty on our new Highway 7 East rapidway, clearing the way for rapid transit. In Markham, the rapidway travels down South Town Centre Boulevard and Cedarland Drive. The glass canopies at vivastations shelter Viva customers from light flurries, but when heavy snow or ice make an appearance, the heated enclosure is where you want to be.  To remove the snow at the stations, a contractor from YRT/Viva operations shovels and salts the vivastation platforms so that they’re safe for everyone. Sidewalks are usually a municipal responsibility, so the new sidewalks along the Highway 7 West rapidway are cleared by the City of Markham and Town of Richmond Hill.

.
Before the rapidway was built on Highway 7 East, sidewalks were few and far between, and there were smaller curb-side Viva stops. The street has now been transformed from a suburban freeway to a walkable urban street and transit route [with bike lanes!]. With the new facelift complete there are benefits for everyone and the same treatment is coming next year on Davis Drive!  Think spring!

Categories
Rapidways

2014 – a year of action

2014 - a year of action

As 2014 draws to a close, we’re pleased to say that each of our projects saw great progress this year. The Bus Rapid Transit projects start and end at different times so each has its own construction schedule to match the unique challenges, such as: length of rapidway, complexity of underground work, and landscape and infrastructure features like hills and bridges. As we progress through these challenges we consider them milestones, and after a year of milestones there are plenty of moments to look back on.

On Highway 7 East in Markham, the second stretch of rapidway opened from Highway 404 to South Town Centre Boulevard, and construction will be complete on the last piece to Warden Avenue by the end of 2014, with some finishing touches to add in spring 2015. This final section allows Viva customers to experience the future of rapid transit in York Region, from Bayview Avenue in Richmond Hill to the Downtown Markham development area. Riders are already seeing up to 35% travel time savings on the rapidways.

In Newmarket on Davis Drive, utilities and telecommunications were relocated to prepare for road widening and building the rapidways in the centre of the road. Road widening continued and base-layer paving was also completed in sections along Davis. Significant milestones included: completing the structure of the Keith Bridge and reopening the Tom Taylor Trail, moving the Union Hotel into its final location and installing the steel structures for the first vivastation at Longford/Parkside. The glass canopies will be installed over the winter and the vivastations at Main Street and Southlake Hospital are also underway. It’s been a busy, messy year but crews are working quickly. We’re in the home stretch with the rapidway set to open December 2015.

Along Highway 7 West in Vaughan, the first phase of rapidways is well underway and a there has been a lot of progress in 2014. Between Jane Street and the CN Bridge, work continues on base-layer paving, building retaining walls and expanding the CN Bridge, and we’re almost done relocating some underground infrastructure. East of Jane Street, the road has been widened and traffic has been shifted, so that work in the centre of the road [including paving, installing vivastations platforms and canopies!] can begin in 2015. The contract for phase two of the rapidways in Vaughan will be awarded in 2015, adding dedicated bus lanes and vivastations from Edgeley Boulevard to Pine Valley Drive and from Bowes Road to Yonge Street [in blue on map]. While some pre-construction activities are already underway, construction is expected to begin in late 2015/early 2016.

On Yonge Street in Richmond Hill and Newmarket, the contractor is working to finalize the rapidway design and construction schedule. Meanwhile, crews are out conducting surveys and utility investigations to make sure we have an accurate record of what’s above and below the ground.

We’re also building a state-of-the-art Operations, Maintenance and Storage Facility in Richmond Hill to act as a ‘home base’ for transit. This nine-acre, 481,679 square foot facility will be LEED® certified [Leadership in Energy and Environmental Design], and is scheduled to be complete mid-2015.

Everyone’s busy making memories during the holidays, but we hope that you’ll have a few moments to see some of our videos that give you a sneak peak at rapid transit in York Region:

Where did it all begin? See the launch of curbside Viva service in 2005. Also see the vision for the transformation of York Region and some of the considerations given to the design of the rapidway vivastation, and take a peek inside the rapidway vivastations.

While you’re watching videos, why not find out what’s happening in your community:

 

 

 

Categories
Construction Rapidways

from messy to marvelous – davis drive year in review

Video: from messy to marvelous - davis drive year in review

It’s an exciting time as the transformation of Davis Drive has made significant progress and is starting to be seen along the corridor.

A lot of progress above ground was made this year and a number of milestones were achieved, all of which clears the way for 2015 and the last year of construction. We thank you for bearing with us through the mess and as we work hard to finish as quickly as possible.

Standing at Yonge and Davis, you can look down Davis Drive and see the installation of boulevards and planters. As you travel to your destination you’ll notice the decorative planters along with interlocking paving stones and concrete sidewalks in areas from Yonge Street to Longford/Parkside Drive.

Construction of the vivastation at Parkside/Longford and Davis is making great progress. The steel structure for the vivastation is in place and the glass for the canopies will be arriving soon.

Construction of two more vivastations at Main and Southlake Hospital are also underway.

The structure of the Keith Bridge has been rebuilt and the Tom Taylor Trail has been restored to its original location under Keith Bridge; which is located just past the GO train station.

VivaNext will be moving to the next phase of rapidway construction where station platforms, canopies and eventually rapid transit bus lanes will be built in the centre of the road. As a result, there will be permanent changes to how motorists use intersections, traffic lanes and access businesses along Davis. New traffic signals have been installed at Yonge, George and Barbara. Drivers can now make dedicated left-turns and U-turns where U-turn permitted signs are posted. From our experience on Highway 7, these new movements help the traffic flow smoother. For more information on these important changes please visit vivanext.com

We captured a number of these accomplishments on video and condensed them into a short clip for your viewing pleasure. The investment in modernizing our roads and revitalizing Newmarket’s infrastructure will go a long way to making sure Davis Drive is built on a solid foundation that will serve the growing needs of Newmarket for many decades to come. We look forward to the rapidway opening in 2015 and bringing Viva service to Davis Drive.

Categories
Construction Rapidways

seeing the transformation unfold on highway 7 west

click here to see the video of 2014 Vaughan rapidway construction

we’ve been busy this year

Construction is well underway for the first phase of vivaNext rapidways in the City of Vaughan, and the transformation can be seen along Highway 7 West. Check out our latest video for an up-close look at the milestones we’ve accomplished this year. Although construction will continue throughout the winter months from Edgeley Boulevard to Bowes Road, here’s an update on the progress made in 2014:

  • Traffic has been shifted east of Jane Street to its final configuration, so that work in the centre of the road [including platforms and canopies] can begin in 2015.
  • As part of the 8-metre expansion of the Canadian National Railway [CN] MacMillan Bridge, we poured over 800 tonnes of concrete to create new columns and bridge pier caps.
  • Underground infrastructure revitalization continues – utility, telecommunications and storm sewer relocation is approximately 80% completed.
  • Road widening is completed and base-layer paving is 90% finished between Jane Street and the CN Bridge. Paving activities will continue in 2015.
  • In order to preserve the existing Black Creek and Hillside Culverts, retaining walls were built. In total, five retaining walls have been completed along the corridor with a few more set to get started in 2015.
  • Important traffic and pedestrian changes can be seen at several intersections. Motorists are benefiting from new turning movements and pedestrians now have two-stage crossings.

We know construction can be messy and disruptive at times, and we thank you for your patience and understanding as we continue the transformation. For up-to-date information on construction progress and activities, visit http://www.vivanext.com/hwy7progress.