the critical role of spiders in building Vaughan Metropolitan Centre Station

Now, before you think we’ve imported some exotic tropical arachnids, what we call “spiders” are actually the stainless steel fittings that hold together the glass pieces on our stations. They’re called spiders due to their shape, and they play a critical role in the architectural and structural design of our stations.

For the new Vaughan Metropolitan Centre [VMC] rapidway station, the main structural support comes from the welded steel superstructure that forms the distinctive curved shape. Over top of that, steel, custom-made spider fittings are bolted to each steel intersection. The spider fittings support the individual glass panels on the station’s sides and skylight.

410 panels of glass

Each triangular-shaped panel of glass is attached by brackets on the legs of the spiders. Because each piece of glass is a unique size and shape, the job of attaching the glass to the spiders is very fiddly. The extra-large 50 by 24 metre VMC canopy has an eye-popping 410 panels, each equally spaced and slightly different due to the station’s curved planes. The tempered glass can’t be cut or drilled on site without shattering, so holes for the brackets were made during the fabrication process.

beautiful precision

We knew if the holes in the glass didn’t line up exactly to the spider brackets, the glass pieces wouldn’t fit. Since glass fabrication is a fairly slow process, we didn’t want to risk having to go back and remake a piece. Rather than making the glass in advance, we installed the spiders, then measured them with a 3-D laser scanner that registered the targets as multiple cloud points; essentially the same process used to make a 3-D model.

The last step was the installation of the glass panels to the station roof, and seeing all this precision and planning come together for beautiful results. Now if you visit the VMC rapidway station, you can take shelter under a strong and stunning glass canopy reminiscent of the great European architectural traditions, right here in York Region.

 

Categories
Commissioning Construction Facilities and terminals Rapidways Safety Stations Technical

beautiful curves of glass

If you’ve ever had to replace a window in your house, you know that working with glass is fiddly, exacting work. It needs to fit perfectly or you’ll get drafts and leaks. Glass has no tolerance for being the wrong shape or size. And dropping a pane from a window: well, that means another trip back to the store.

Now, imagine the challenges of installing the glass on the curves of our new Vaughan Metropolitan Centre [VMC] rapidway station. As you can guess, it was a long, multi-stage process, done with great care and precision.

strength and safety

As with all our vivastations, the VMC glass was laminated and tempered for strength and safety. First the glass was cut into panes, and then it went through a special process to make it extra strong. This way, if it breaks, it crumbles into small granular chunks instead of sharp pieces.

To add more strength and make it even safer, we then laminated the tempered glass by sandwiching two glass sheets together around an interlayer. If the glass is broken, the interlayer holds the small pieces together instead of breaking into many little shards, the same way a car windshield stays together in an accident. The interlayer on the blue skylight glass is actually a different, stronger material than the interlayer used for the clear side glass, since the top skylight needs to support heavier loads from snow and maintenance workers.

creating curves

Fitting flat glass to the curved shape of the station was a challenge, because every surface of the steel roof curved over two dimensions, much like the outside of a ball. The first step was to divide the glass into a series of triangles. Three-sided shapes are easier to work with compared to four-sided shapes, the same way a tripod is more stable on uneven ground compared to a four-legged chair.

But this still left the challenge of fitting flat pieces of glass over a curved frame. The solution here was to adjust the bolts on the corners of the spiders [the stainless steel fittings that hold  the glass pieces onto the frame] so they’re each set at a different height. We knew how high each bolt needed to be from 3D scans, so we adjusted them before we installed the glass. By installing each corner of glass at a slightly different height, we recreated the curves of the tubular steel frame.

intricate jigsaw puzzle

The last step was putting the glass panels in place, one by one. Although they were all triangles, every piece was unique like pieces of a jigsaw puzzle, so to avoid mix-ups they were carefully numbered before they were delivered. Once the glass panels were bolted onto the spiders and the final adjustments made to perfect the curve of the glass, we sealed the gaps with caulking to make the structure weather-tight.

Building this strong and beautiful glass-covered station took precision, but look at the stunning results! This landmark station helps set the architectural stage for future development at the VMC and makes the everyday experience of transit a beautiful one for our customers.

Categories
Commissioning Community Events Facilities and terminals General Innovation Rapidways Stations Subways

amazing team, extraordinary results

What a week it has been! The launch of the TTC Line 1 subway extension with the Highway 7 West rapidway and vivastation on Sunday in Vaughan is one of those lifetime moments. We’re going to remember this day for the rest of our lives. This is the day everything became a little closer, and a lot faster for York Region and the City of Vaughan.

unwavering dedication

For everyone involved, including us at York Region Rapid Transit Corporation, it was an exhilarating and emotional weekend, the culmination of years of incredible challenges and unwavering dedication, everything we’ve been working toward for a very long time! Many of us shouted and cheered as the first train pulled into the new subway station.

Then, seeing that Viva bus roll down the red asphalt rapidway into the open, airy Vaughan Metropolitan Centre vivastation and pick up actual passengers who came up the stairs from the subway – well, it’s hard to describe the feeling, except to say that more than a few grew a little misty-eyed! So many people came out to mark this milestone day for transit in the Greater Toronto and Hamilton Area, we know how much these new transit connections matter and we thank you for your patience during the long construction period.

#AnEngineerWasHere

Kudos goes out to the engineers, planners and project team, whose tireless drive moved the VMC station and rapidway project forward every step of the way: from the environmental assessments to the design to breaking ground, from utility relocations to storm sewer work and road widening. Along with the many contractors, they pushed though good and bad weather, scalding heat, freezing cold and everything in between. They worked through paving and bridge reconstructions, to timelines off schedule and on again, to the construction of our vivastations and our landmark Vaughan Metropolitan Centre vivastation. Experts from many agencies, cities and private companies all came together to make this day happen.

Now we have incredible, tangible results with the first subway-BRT connection, a legacy that will keep our Region moving for years to come. Just goes to prove anything is possible with extraordinary teamwork, unwavering dedication and an eye to the future. Again, thank you for supporting this project and we hope you get out and try the new system!

Categories
Announcements Commissioning Community Events Construction Facilities and terminals Rapidways Stations Subways

Subway and new Viva connections NOW OPEN in Vaughan!

This morning, the first subway carrying transit customers arrived in York Region, forging a historic connection between bus rapid transit and subway. Now, everyone can experience seamless transit connections in Vaughan! The vivaNext rapidway and new landmark vivastation also opened for service this morning with an epic celebration at Vaughan Metropolitan Centre [VMC], alongside the TTC Line 1 subway extension opening. Viva la subway!

Read the news release.

even more transit connections

Now the transit connections available to customers simply go further and faster. The rapidway-subway connection marks a tipping point for transit in York Region, amplifying the power of the Viva rapid transit network.

The VMC area is a transit powerhouse, home to two new stations: the landmark Vaughan Metropolitan Centre vivastation and the Vaughan Metropolitan Centre subway station – the new terminus of TTC Line 1. In a few months, the SmartCentres Place Bus Terminal will make the VMC area even better, connecting YRT buses to both stations with a pedestrian tunnel.

true city building

There’s no doubt – your destination has arrived! The new VMC development is true city-building on an epic scale, built on the foundation of strong transit connections. Not only does rapid transit transform how people move in our Region, it changes how we live – for the better. Stronger economies, more jobs, and walkable, livable, desirable communities: it’s the driving force behind York Region’s Transportation Master Plan and the reason we build rapid transit.

On an even larger scale, strong connections like these that cross regional borders are crucial to the Greater Toronto and Hamilton Area [GTHA], and a key strategy of the Metrolinx Draft 2041 Regional Transportation Plan.

Thank you!

Now we can see the network take shape in York Region, with three rapidways running, two more underway and an actual subway connection!

Changes of this magnitude are fueled by the power of collaboration and funding partnerships. Our rapidway projects are funded by the Province of Ontario, and our other projects are funded by a combination of Federal, Provincial and Regional contributions. SmartCentres Place Bus Terminal even includes some private funding for the pedestrian tunnel.

We’ve all come a long way together, and we thank you for your patience during construction. Now, we hope you enjoy the ride!

Categories
Announcements Commissioning economic & financial Facilities and terminals Innovation Rapidways Stations Subways

The ribbon is cut! Trudeau and Wynne came! Now only two days until subway meets BRT!

This historic weekend of transit firsts in Vaughan kicked off in style.

Prime Minister Justin Trudeau joined Premier Kathleen Wynne, Toronto Mayor John Tory and many other dignitaries to officially cut the ribbon on the Line 1 subway extension, at Vaughan Metropolitan Centre [VMC]. Then, they rode the subway from the VMC station to the new York University subway station for a press conference.

“The Toronto-York Spadina Subway Extension will mean a faster commute, less time in traffic and more money in people’s pockets as they trade their cars for a subway ticket,” Prime Minister Trudeau told the crowd at York University station.

That’s music to our ears!

The crowd included partners from all three levels of government, who worked together to make this project a reality. Also on hand were many members of our vivaNext team, who played a key role in this project, working with the TTC on the York Region stations. Joining the crowd were the many partners who helped make this happen.

three subway stations in York Region!

In just two days, York Region will have three shiny, new subway stations open for service: Pioneer Village, Highway 407 and the end of the line, Vaughan Metropolitan Centre. On opening day and Monday, members of our team will be on hand to answer your questions and help you find your way.

Our brand new, flagship bus rapid transit station will greet riders at the VMC, forging the connection between our rapid transit network in York Region and the new subway.

Also coming later this month is the GO train connection at the new Downsview Park station, where commuters on the Barrie GO train can connect to the Line 1 subway extension.

“If we build it, they will come”

Now, with the 8.6-kilometre subway extension, downtown is a mere 42 minutes away, but we expect subway traffic to flow both ways. Wayne Emmerson, York Region Chairman and CEO, said, “If we build it, they will come.” He called the subway a “once in a lifetime opportunity,” saying it “will help further develop an urban community that is transit-oriented, forward-thinking and has economic development opportunities to benefit current and future generations.”

“Big transit takes time”

Premier Wynne acknowledged the time and effort of all levels of government that came together to connect the heart of York Region to downtown. She also gave a nod to our new Highway 7 West rapidway, saying that downtown foodies can hop the vivaNext rapid transit system to restaurants in Richmond Hill.

But she summed it up best with: “What an amazing day this is!”

We agree, Premier Wynne! And this Sunday will be even better, when the subway and our rapidway open for service, and you can experience the ride firsthand. It’s going to be a rush! We hope to see you there.

Categories
Commissioning Construction Facilities and terminals General Rapidways Stations Technical Traffic signals

proof of performance

The days are counting down and the excitement is growing. The launch of our extraordinary new vivastation at Vaughan Metropolitan Centre, along with the ground-breaking TTC Line 1 subway extension and our rapidway, is only four days away. Now we have one last crucial task to complete before our gorgeous new station joins the transit mega-hub at the VMC: we need to carry out commissioning.

testing, one, two, three

Commissioning of the new bus rapid transit station is similar to the process we do for all our new stations, rapidways and facilities. Very simply, it means confirming everything we installed, from the heaters and automatic doors in the passenger enclosures, to the cameras, speakers and variable message signs [VMS] on the platforms, works the way it’s supposed to.

Before their work is done, our builders have to test every single device and piece of equipment to demonstrate they met all their obligations. The station has complex equipment for fares and security, and all the general building components like lights, plumbing, and electrical connections. Systems connect to the central York Region control room, enabling them to see the platforms, hear the speakers, run messages on the VMS and communicate through emergency call buttons. During commissioning, every light switch, outlet and connection is tested. Our builder also works with the new station owners, YRT/Viva, to help them assume operation.

smart systems

The new station is part of a highly sophisticated system which includes the broader rapidway network and its whole range of intelligent transportation system [ITS] features. ITS is really the reason Viva is able to operate as a rapid transit service, keeping our system running on time with supervision from YRT/Viva’s central control room.

trial run

A critical part of commissioning is testing the newly finished components in the new VMC station and the surrounding rapidway, to make sure they’re all connected properly to the control room and the rest of the system. Testing for full integration requires that we run buses through the new rapidway for a day. During that process, we’ll make sure that all the traffic-related components are communicating properly to the buses and to the general system, and ensure the traffic signal timing is set for optimal travel times.

This station has one more layer of complexity beyond the other stations we’ve built, because of its connections to the TTC. We need to check every interface with the TTC system, which includes electrical connections running between our station and their panels below.

Commissioning is the final step, and you can see why it’s so important to do it carefully and methodically. Because of that complexity, some work will continue on the station in 2018. But once it’s finished, get ready to celebrate and enjoy faster transit with us!

Categories
Announcements Commissioning Community Events Construction Facilities and terminals General Rapidways Stations Subways Urban Planning

Transit gets epic in Vaughan this Sunday

Get ready for the game-changer. Transit is about to get epic at the Vaughan Metropolitan Centre [VMC], and you’re invited. On Sunday, December 17, this public launch event is set to change the face of transit forever in York Region.

The public opening of the TTC Line 1 Subway Extension will make history, as the first subway ever in York Region brings transit customers up to Vaughan Metropolitan Centre.

Today was another great day for integrated transit connections in the York Region and the GTHA – as we celebrated the official opening of the newest bus rapid transit [BRT] rapidway segment and Vaughan Metropolitan Centre [VMC] Station on Highway 7 West. This new vivastation will be fully connected to the new VMC subway station.

Bus rapid transit meets subway for the first time!

you’ll be moved!

The new rapidway section runs west of Jane Street to Edgeley Boulevard, with dedicated centre lanes that will whisk riders to the VMC with faster and more consistent travel times. Including the previously completed section, the rapidway will run the full 3.6 kilometres from Bowes Road to Edgeley, the bus-only lanes clearly marked for drivers with red asphalt.

Coming in 2018, SmartCentres Place Bus Terminal will complete the transit powerhouse at VMC, as YRT buses begin providing services from this stunning new bus terminal.

an extraordinary station

Along with the rapidway comes an extraordinary vivastation for a new downtown destination – the Vaughan Metropolitan Centre rapidway station. The design supersized our traditional vivastation arched glass canopies, inspired by historic and modern European transportation architecture. The open, airy, domed glass canopy shelters the road and station.

the future is now

It’s only 43 minutes via subway to downtown from the VMC, but there’s no need to go anywhere. If you’re at Vaughan Metropolitan Centre, you’ve already arrived!

Welcome to the brilliant future of transit-oriented development, right here, right now in York Region. The VMC shows what it’s all been about: rapid transit connections that fuel livable, walkable, desirable communities, spur jobs and economic growth, creating places where we all want to live, work and play.

 

Categories
Commissioning Construction Facilities and terminals Rapidways Stations Subways Technical

collaboration now and for the future

Building our Vaughan Metropolitan Centre rapidway station required close collaboration with the TTC, since it’s so near to their new subway station – literally on top of it, in fact! The collaboration began at the design stage, and continued between our two construction teams as we brought the plans to life.

staging for success

With the new rapidway station being built in layers, and in the middle of the road, staging was crucial for both the vivaNext team and TTC. Staging means carrying out work in phases, such as shifting traffic lanes from side to side to give crews room to work safely. Another example was how we stayed clear of the TTC work crews while they finished the subway box, before we started on the concrete and rebar that went on top.

teamwork

Coordinating with the TTC, vivaNext crews shifted the traffic to one side while we built the road on the other side, and they worked on that side of the underground subway structure. Then, when we flipped the traffic back to widen the other side, the TTC also switched sides. A detailed planning process ensured we both did what we needed to do, in the right order and the shortest possible time, without tripping over each other.

Building the escalators and elevators from the TTC station to the BRT station also took detailed planning and coordination. Rules and specifications determine how closely crews can work to adjoining crews. The subway and rapidway stations share a very small area. If you’ve ever done a renovation, this was like having one group building the stairs, and another building the walls and hanging the wallpaper.

the collaboration continues

Most of that coordination is done now, with the vivastation area fully under our contractor’s control. We’ll continue to work closely with the TTC as we get to the final stages of signoff for the station equipment. On opening day, December 17, there may be some finishing touches still required, but we will open for service!

The collaboration continues even after the work is done, since the goal of the new station is to create seamless connections between Viva rapid transit and the TTC. We’re looking forward to a long, happy future of working together to get you where you want to be.

Categories
Commissioning Construction Design Facilities and terminals Innovation Rapidways Stations Technical

the crowning touch

Ready for the crowning touch? The new SmartCentres Place Bus Terminal comes with a mesmerizing pièce de résistance – a sweeping, curved wooden roof, as beautiful as it is functional.

Reminiscent of West Coast style, the horseshoe-shaped roof shelters the outdoor bus stations in beautiful elegance. A fluidity breathes life into the design, curving in a slight v-shape from the outside in, and rising up at the wingtips and the saddle. You can almost feel the motion, very fitting for a bus terminal with YRT/Viva services branching out across York Region.

an intricate jigsaw puzzle

The simple elegance of the roof belies the complexity of its creation. The wood pieces need to look curved, but they are flat. Custom-cut to the architect’s design, they fit together with the steel substructure, which was also designed in custom pieces.

It’s like a very complicated jigsaw puzzle. Every section is numbered and assembled with exact precision. When the flat pieces fit together, they create the appearance of a curved roof. High-strength glued-laminated timber beams support the roof, running vertically and also lengthwise.

Not only does the wood look stunning, it was a cost-effective choice and is Forest Stewardship Council (FSC) certified to York Region standards. When it’s finished, it will be stain-coated with intumescent fire-retardant material.

 a showstopper for a new downtown

The result is an eye-catching landmark – a roof that draws the eye and a terminal where you can pass the time in style. After all, SmartCentres Place Bus Terminal is not your run-of-the-mill bus station. As part of the vibrant, new downtown flourishing at Vaughan Metropolitan Centre, this bus station needs to look the part.

Set to open in 2018, the Terminal will complete the transit powerhouse at the VMC: subway, rapidway and YRT/Viva terminal, working together to move you, faster and easier than ever before.

Categories
Commissioning Construction Facilities and terminals General Rapidways Safety Stations Technical

the concrete choice

If you’ve ever renovated your home, you know about the endless options for flooring: tile, wood, carpet, stone. Once you select your material, you have to make more choices about colour, finish, how it should be arranged, even the kind and colour of grout. So many decisions! Of course, as with all design questions, your choices are shaped first and foremost by the space and its function: wet or dry? Formal or casual? How much wear will it get?

the floor dilemma

Our design teams faced similar quandaries when working out the details for the rapidway platform floor of the new Vaughan Metropolitan Centre Station [Viva bus rapid transit].

All of our other open air vivastations have tiled platform floors, so the obvious choice would be to use that in the new VMC Station. But this station faced an additional level of complexity, being built above the subway extension.

The top of the subway station extends to just under the vivastation foundation, providing limited depth to work with. Installing the tiles with concrete underneath as required would use up space needed for essential power and communications cables. A concrete floor became the ideal alternative.

durable by nature

Concrete flooring for the platform works better in the space we have, and the durability means less maintenance is required, saving money down the road. The VMC Station floor will be getting a lot of use in a relatively small space. We know concrete will perform.

But, we also want great aesthetics. Fortunately, concrete is also versatile.

Outside the station along the sidewalks of Highway 7 are paver stones laid in a distinctive pattern. Inside the station, we’re re-creating that look with concrete. First, we built the concrete molds to match the sidewalk, then poured each section with matching colours of concrete.

functions like concrete, looks like tile

Because the platform floor continues beyond the shelter of the vivastation canopy, we needed to ensure it’s not slippery. Before the concrete set, every concrete slab was given a hand-applied swirl finish to provide a measure of slip-resistance. We have also done decorative work on each section to create the appearance of tile.

Just like you’d want for your own home, the final result will meet design goals in every way: strong, durable, easy-to-maintain, and functional. And nice to look at, too.