testing, testing, testing

testing, testing, testing

As you will know from driving along Highway 7 East from Highway 404 to Warden, our rapidway construction is really coming along, and this summer another segment will be going into operation. We still have a bit more work ahead of us before service operation can begin, including some work which will be obvious, such as final paving, striping and landscaping. But in addition to that, we’re just getting underway on a less-obvious but highly important part of the job, which is testing – to ensure that all parts of the rapidway project are ready for active service.

This stage – known in the construction world as commissioning – is critically important and planning for commissioning the new section of Highway 7 East rapidway has already been in progress.

So what does commissioning involve, and how do we do it?

First of all, the technical definition of commissioning is: the process of assuring that all systems and components of a system are designed, installed and tested according to the operational requirements that have been established.

In the case of vivaNext, the most visible components of the project include the new roadways, passenger stations and amenities, and streetscape elements such as lighting, sidewalks and landscaping. Ongoing inspections are being done as construction progresses to ensure that these are being built to certain specifications, before they are handed over for use by Viva. Commissioning is a detailed focus on the key systems and components that together make up the overall network.

These components include the fare collection equipment; the station information systems such as the variable message signs, clocks and Public Address systems; passenger security elements such as closed circuit TV systems and emergency call buttons; and the traffic signals at intersections. It also includes the sophisticated Transit Vehicle Detection system, which will provide information to the traffic signals when rapid transit vehicles are approaching intersections, as well as the overall communications system and fibre optic network that links all of these components.

Testing starts at the factory, where the fabricator verifies that the equipment works as it was intended to, and then each component is tested again once it’s installed. Once all the components are installed and each one is confirmed to be working as designed, a series of additional tests are carried out to confirm that the entire system is integrated properly and working together. Don’t forget we have to connect up to the section already open and make sure everything continues to run smoothly.

The final step involves testing the reliability and function of the extended system, including simulating actual operation using buses and staff acting as passengers. This gives the people who will be involved in the future operation, maintenance and service of the rapidway an opportunity to become familiar with the new section.

So you can see that there’s still a lot of work behind the scenes to get to the day we’re all looking forward to – when the Viva bus extends its journey the length of the new rapidway from Bayview Avenue to South Town Centre Boulevard in late August.